Construction Update

Brattleboro NH PC 25(6)

Brattleboro NH PC 25(5)

Brattleboro-Putney PS 25(11)

DATE: Friday, October 24, 2025


Due to the Halloween Holiday on Friday, October 31st, 2025, crews will postpone their construction start as needed to accommodate trick or treaters.


TRAFFIC IMPACTS:


Brattleboro NH PC 25(6)

Nighttime single-lane closures will be in place as needed Monday night through Saturday morning from 7:00 p.m. to 6:00 a.m. for work on Vermont Route 9 (Western Avenue and High Street), U.S. Route 5 (Main and Canal Street), and Vermont Route 30 (Linden Street). Flaggers will be present to direct one-way alternating traffic through the work zones. Motorists should watch for wet paint.


Brattleboro-Putney STP PS 25(11)

Nighttime single-lane closures will be in place as needed Monday night through Saturday morning from 7:00 p.m. to 6:00 a.m. on U.S. 5 (Putney Road) from the intersection with Vermont Avenue to the approximate intersection with Noah's Lane. Flaggers will be present to direct one-way alternating traffic through the work zones.


Daytime single-lane closures are scheduled to begin next week on U.S. 5 from the Brattleboro/Dummerston town line progressing north toward the project limits in Putney. Flaggers will direct alternating traffic patterns through the work zones.


Milling the bridge on U.S. 5 (Putney Road).

PARKING IMPACTS:


Overnight parking restrictions throughout downtown may be enforced during working hours in areas where paint has not yet been applied. Street side parking will be unavailable on VT 9 (Western Avenue and High Street). From 7:00 p.m. to 6:00 a.m. Monday night through Saturday morning, construction operations are scheduled in multiple locations throughout the project. To see alternative lots with rates and hours, please go to https://brattleboro.gov/parking.

CONSTRUCTION ACTIVITIES:


Crews continue to measure decibel levels with noise monitoring equipment through the work area.


Brattleboro NH PC 25(6)

The Class 1 paving project is finishing up throughout the downtown. Crews are working on VT 9 (Western Avenue and High Street) and will be finishing up in areas on U.S. 5 (Canal Street and Main Street). Work to be done includes hand painting (symbols, stop bars, crosswalks, etc.), sign installation, and some signal work.


Brattleboro-Putney STP PS 25(11)

Between Vermont Avenue and Noah's Lane, crews will continue working in this area and the paint operation will move here once everything in downtown is complete.


Crews plan to begin working on the ditches beside U.S. 5 during day shifts starting next week. Work will continue from the Brattleboro/Dummerston town line north toward Putney.


To view and share this email as a webpage, please utilize the link below:


View as Webpage

LOCATION:

This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating "State Highway Ends" and "State Highway Begins". Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.


Brattleboro PC25(5)

VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.


Brattleboro PC25(6)

U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.


VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.


VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.


VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.


Brattleboro-Putney STP PS25(11)

U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.


BRATTLEBORO NH PC25(6) INTERIM COMPLETION: Fall 2025


OVERALL PROJECT COMPLETION: Fall 2026

Contact Information:

Name - Bethany Oprendek

Phone - 802.267.4044

Email - bethany@bbo-enterprises.com