Construction Update

Brattleboro NH PC 25(6)

Brattleboro NH PC 25(5)

Brattleboro-Putney PS 25(11)

DATE: Friday, November 21st, 2025


Due to the Thanksgiving Holiday, crews will be off the project by Noon on Wednesday, November 26th.


TRAFFIC IMPACTS:


Brattleboro NH PC 25(6)

Crews will be working off the shoulders during the day and motorists should be vigilant.


Brattleboro-Putney STP PS 25(11)

Work is finishing up on U.S. 5 (Putney Road) from the intersection with Vermont Avenue to Noah's Lane. Nighttime single-lane closures will be in place as needed Monday and Tuesday nights from 4:00 p.m. to 6:00 a.m. with flaggers present to direct one-way alternating traffic through the work zone.


Daytime single-lane closures are scheduled to continue next week on U.S. 5 in Dummerston progressing south Monday through Wednesday. Flaggers will direct alternating traffic patterns through the work zones.

Ditch work on U.S. 5 in Dummerston.

CONSTRUCTION ACTIVITIES:


Brattleboro NH PC 25(6)

Crews will be working to remove construction approach signs next week during the day.


Brattleboro-Putney STP PS 25(11)

Between Vermont Avenue and Noah's Lane, crews are finishing up their final work items. Much of this work is weather dependent and the contractor has been allowed to work earlier in the afternoon, when temperatures are more favorable, to complete the final painting. Whatever cannot be accomplished by the end of this week will continue next week before the holiday.


Crews are making progress on the ditch line work on U.S. 5 during the day. They have continue to coordinate their work zone with the power company and work from north to south. They plan to work Monday through Wednesday on this and return after the Thanksgiving holiday to finish up in the area.


To view and share this email as a webpage, please utilize the link below:


View as Webpage

LOCATION:

This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating "State Highway Ends" and "State Highway Begins". Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.


Brattleboro PC25(5)

VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.


Brattleboro PC25(6)

U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.


VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.


VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.


VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.


Brattleboro-Putney STP PS25(11)

U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.


BRATTLEBORO NH PC25(6) INTERIM COMPLETION: Fall 2025


OVERALL PROJECT COMPLETION: Fall 2026

Contact Information: