Construction Update

Brattleboro NH PC 25(6)

Brattleboro NH PC 25(5)

Brattleboro-Putney PS 25(11)

DATE: Friday, August 8, 2025


TRAFFIC IMPACTS:


Nighttime single-lane closures will be in place next week on Monday night through Saturday morning from 7:00 p.m. to 6:00 a.m. Work will continue on Vermont Route 9 (Western Avenue and High Street), U.S. Route 5 (Canal Street and Main Street), and Vermont Route 30 (Linden Street). Flaggers will be present to direct one-way alternating traffic through multiple work zones. Motorcyclists should watch for grooved and uneven surfaces and all motorists should be aware of raised utility structures in the travel lanes and shoulders.


Parking restrictions will be enforced during working hours. Pedestrians should watch for sidewalk detours in place on Canal Street (U.S. 5) and on Western Avenue and High Street (VT 9).

Paving the first layer or "Shim" coat on VT 9.

Drainage structure repair on U.S. 5.

PARKING IMPACTS:


Street side parking will be unavailable on Main Street and Linden Street from 7:00 p.m. to 6:00 a.m. Monday night through Saturday morning. Other areas where parking restrictions will be enforced are on Canal Street Monday and Tuesday nights. Friday night work zones are being limited to certain areas so as not to interfere with downtown parking for events and businesses. Please pay attention to nightly message boards indicating parking restrictions. The contractor and Brattleboro DPW are working together to move these boards for locations of work each evening. There will not be a parking ban along the street unless work is being done that night. Please see the infographic below for locations of work and parking restrictions. To see alternative lots with rates and hours, please go to https://brattleboro.gov/parking.

Phasing and Parking Information

CONSTRUCTION ACTIVITIES:


Canal Street (U.S. 5) - Crews are finishing up utility structure work and anticipate being done with this work on Tuesday night next week. Work on ADA compliant sidewalk ramps will begin on Monday night.


Western Avenue and High Street (VT 9) - The leveling layer or "shim" pavement has been placed on VT 9 with the exception of some side roads that should be finished up this week. Once the sidewalk crew has finished all ramps on Canal Street, they will begin work here.


Linden Street (VT 30) and Main Street (U.S. 5) - The contractor will be prioritizing this corridor next. Milling and pothole repair will be completed this week. Paving of the leveling layer of pavement will begin Monday night and continue through Friday night. The structure crew will follow behind this paving crew and begin to work on the utility structures in these areas.


Crews will have noise monitoring equipment to measure decibel levels over the course of the evening.

If you are being forwarded this message and would like project communications sent directly to your inbox,

please click the button below:


To view and share this email as a webpage, please utilize the link below:


View as Webpage

LOCATION:

This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating "State Highway Ends" and "State Highway Begins". Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.


Brattleboro PC25(5)

VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.


Brattleboro PC25(6)

U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.


VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.


VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.


VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.


Brattleboro-Putney STP PS25(11)

U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.


BRATTLEBORO NH PC25(6) INTERIM COMPLETION: Fall 2025


OVERALL PROJECT COMPLETION: Fall 2026

Contact Information:

Name - Bethany Oprendek

Phone - 802.267.4044

Email - bethany@bbo-enterprises.com