Construction Update

Brattleboro NH PC 25(6)

Brattleboro NH PC 25(5)

Brattleboro-Putney PS 25(11)

DATE: Friday, September 12, 2025



TRAFFIC IMPACTS:


Nighttime single-lane closures will be in place Monday night through Saturday morning from 7:00 p.m. to 6:00 a.m. Work will continue on Vermont Route 9 (Western Avenue and High Street), U.S. Route 5 (Canal Street and Main Street), Vermont Route 30 (Linden Street) and Vermont Route 142 (Vernon Street). Flaggers will be present to direct one-way alternating traffic through multiple work zones. Motorcyclists should watch for grooved and uneven surfaces. All motorists should be aware of raised utility structures and wet paint.


Parking restrictions will be enforced during working hours. Pedestrians should watch for sidewalk detours.

Concrete ramp removal on VT 142.

PARKING IMPACTS:


Street side parking will be unavailable and strictly enforced on all project routes. From 7:00 p.m. to 6:00 a.m. Monday night through Saturday morning, please pay attention to nightly message boards indicating parking restrictions. The contractor and Brattleboro DPW are working together to move these boards for locations of work each evening. To see alternative lots with rates and hours, please go to https://brattleboro.gov/parking.

Phasing and Parking Information

CONSTRUCTION ACTIVITIES:


Linden Street (VT 30) - Crews have completed the curb and guardrail installation. Paving is scheduled to begin through here tonight (Friday) and then continue on Tuesday next week. Ramps and sidewalk removals are also scheduled for next week.


Vernon Street (VT 142) - Roadway widening is finished through here. Paving of the first layer of pavement will be complete this week. The utility structure crew will be working through here and paving the final lift of pavement is scheduled for late next week.


Canal Street (U.S. 5) - Permanent pavement marking applications are scheduled to be finished next week. Motorists should be vigilant throughout the corridor and follow flagger instructions as well as avoid any traffic control devices as they may be guarding wet paint on the road.


Western Avenue and High Street (VT 9) - The sidewalk crew and utility structure crew work will continue to make progress on this corridor.


Main Street (U.S. 5) - Sidewalk ramp demolition is planned for next week. Layout for the paving operation is being conducted in anticipation of this beginning next week.


Crews continue to measure decibel levels with noise monitoring equipment.


To view and share this email as a webpage, please utilize the link below:


View as Webpage

LOCATION:

This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating "State Highway Ends" and "State Highway Begins". Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.


Brattleboro PC25(5)

VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.


Brattleboro PC25(6)

U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.


VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.


VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.


VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.


Brattleboro-Putney STP PS25(11)

U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.


BRATTLEBORO NH PC25(6) INTERIM COMPLETION: Fall 2025


OVERALL PROJECT COMPLETION: Fall 2026

Contact Information:

Name - Bethany Oprendek

Phone - 802.267.4044

Email - bethany@bbo-enterprises.com