Construction Update

Brattleboro-Putney PS 25(11)

Brattleboro NH PC 25(5)

Brattleboro STP PC 25(6)


DATE: Friday, August 21, 2026


No Friday overnight work is scheduled for tonight August 21, 2026.



No Interstate 91, Exit 3 closures will be necessary for the remainder of the project.


TRAFFIC IMPACTS:


Vermont Route 9: (Night Work)

Single-lane closures with alternating traffic patterns controlled by flaggers will be in place between the Edward Heights intersection and the Interstate 91, Exit 2 interchange. Monday night through Friday morning, work zones will be active from 7 p.m. to 6 a.m. Delays may be encountered particularly at the beginning and end of shift Tuesday through Thursday.


U.S. Route 5: Brattleboro (Night Work)

A mobile work zone is scheduled from Monday at 7 p.m. to Tuesday at 6 a.m. on U.S. 5 between Noah's Lane through the Exit 3 roundabout to Old Ferry Road intersection for pavement markings. Motorists should watch for wet paint.


From 7 p.m. to 6 a.m. Tuesday through Friday morning, single-lane closures will be in place from Noah's Lane to Old Ferry Road intersection with flaggers and uniformed traffic officers assisting traffic through alternating traffic patterns as needed.

U.S. 5 material transfer vehicle.

CONSTRUCTION ACTIVITIES:


Vermont Route 9: (Night Work)

Weather permitting, final pavement is scheduled for Tuesday through Thursday from 7 p.m. to 6 a.m. The contractor is planning to pave beginning at the western end of the project progressing east to the Exit 2 interchange. Delays may be encountered with this operation.


U.S. Route 5: Brattleboro (Night Work)

Permanent pavement markings will be placed on U.S. 5 throughout next week. Long lines are planned to be placed under a mobile work zone on Monday and symbols and other hand work will be applied Tuesday through Friday morning under single-lane closures. Another crew will be installing bridge joints on a bridge just south of the Exit 3 roundabout and on a culvert just west of the roundabout. This work will also be performed under single-lane closures.


To view and share this email as a webpage, please utilize the link below:


View as Webpage

LOCATION:

This contract is a composite of three separate paving projects with detailed locations listed below. It includes all Class 1 limits of Brattleboro which are typically noted by a sign stating "State Highway Ends" and "State Highway Begins". Work to be done on these projects includes coarse milling (grinding off the top layers of pavement) to a depth of 2 inches and paving a ½ inch leveling course and then a 1 ½ inch top course of asphalt. ADA evaluation of sidewalk and pedestrian crossings, sign replacement, guardrail repair and replacement, center line rumble strip location evaluation and installation, drainage work, and other highway improvements are also planned as a part of these projects.


Brattleboro PC25(5)

VT 9: The project begins at Edward Heights intersection and extends approximately 1.7 miles east to the I-91 Exit 2 interchange.

Brattleboro-Putney STP PS25(11)

U.S. 5: The project begins on U.S. 5 in Brattleboro at the “State Highway Begins” sign at the intersection with Vermont Avenue and extends northerly along U.S. 5 for approximately 8.0 miles to just north of the Putney Landing Road intersection in Putney. Work will also take place within the roundabout and from the roundabout east to the New Hampshire state line on VT 9.

Brattleboro PC25(6) - Substantially Complete in 2025

U.S. 5: The project begins at the intersection with Generous Street and extends approximately 1.9 miles north to the Vermont Avenue intersection.


VT 9: The project begins at I-91 Exit 2 interchange and extends approximately 1.0 mile east to the intersection with U.S. 5 at the traffic signal.


VT 30: The project begins at the U.S. 5 and VT 30 interchange and follows VT 30 three tenths of a mile north to approximately the intersection with Cedar Street.


VT 142: The project begins at the Class 1 limit sign just south of the railroad tracks near Riverside Drive and follows VT 142 north to the intersection with U.S. 5 at the traffic signal, skipping over the newly paved portion of VT 142 completed for the Brattleboro-Hinsdale bridge project.


OVERALL PROJECT COMPLETION: Fall 2026

Contact Information: