The Grindstone Bridge Construction Project limiting traffic to one lane on the bridge was expected to start on May 12. That date has been pushed back due to required pre-construction repairs. Please see the notification received from the City of Hamilton:
On-site engineers reviewed the condition of the portion of bridge that is to remain for this year and a significant amount of repair work was identified. The extent of repair work is more than anticipated and will require about a month to complete. During this work the traffic will need to be shifted to the south side of the bridge, two lanes, one in each direction. The lane shift is required for the workers to repair the north side prior to putting all the traffic on it. Following this work, the traffic control setup with one lane on the north side will be implemented.
The City will share an updated schedule and traffic control plan for the traffic shift to the south side this week.