Installation Update: Remaining Fall Work

Thank you for your continued interest in this project. Below is an overview of the remaining work on the project. This is the last regularly scheduled update, but expect additional updates as work is finished.


Have questions? Contact awolfe@cambridgema.gov.

 

Complete: Flex posts

Westbound Broadway at Felton Street


All flex post installations are complete.

Photo of recently installed flex-posts

Upcoming: Pavement Markings

Lee St to Quincy St


What to Expect: Most pavement markings are installed, except for symbols and green.


When: This work will take place sporadically throughout the remainder of the year.


Impacts: None. Work will take place overnight with minor disruption.

Update: Precast Curb Installation

Ellery St to Quincy St


What to Expect: Concrete curbs, similar to those used on Brattle St, separating the bike lane from the rest of traffic.


When: This work is delayed due to difficulty finding a contractor and supplyer for a new type of curb. The installation schedule is unknown at this time.


Impacts: Daytime work. Some traffic disruptions, including bike lane closure, but no full street closure.

Upcoming: Bus Stop Railing and Shelter

@ Felton St


What to Expect: Additional bus stop improvements.


When: This work is expected to take place in late October or November. The installation is not currently scheduled. We are awaiting additional information


Impacts: Daytime work. Some traffic disruptions, including bike lane closure, but no full street closure.


Upcoming: Signal Changes

Broadway @ Prospect, Broadway @ Ellery St, Broadway @ Trowbridge St


Broadway @ Prospect St

What to Expect: The signal will be programmed to allow dedicated time for left turns.


When: Paving is anticipated to begin in early October. Markings and signal changes will follow.


Impacts: Signal changes will be installed during the day. Expect travel disruption at the intersection only.


Broadway @ Ellery St

What to Expect: New traffic indications will be installed to facilitate a diagonal movement for the east bound cyclists.


When: Signal changes are expected in October depending on contractor availability.


Impacts: Signal changes will be installed during the day with minimal impacts on traffic.


Broadway @ Trowbridge St

What to Expect: New traffic signal indications.


When: Signal changes are expected in November depending on contractor availability.


Impacts: Signal changes will be installed during the day with minimal impacts on traffic.

Contact Us


Andreas Wolfe, (he/him)

Street Design Project Manager, Department of Transportation

617-349-9162 awolfe@cambridgema.gov


Leah Grodstein, (she/her)

Street Design Project Manager, Department of Transportation

lgrodstein@cambridgema.gov

Accessibility Information

The City of Cambridge does not discriminate, including on the basis of disability. We may provide auxiliary aids and services, written materials in alternative formats, and reasonable modifications in policies and procedures to people with disabilities. For more information contact the Department of Transportation at cdot@cambridgema.gov, 617-349-4700 (voice), or via relay at 711.

City of Cambridge

Department of Transportation

Keep in Touch!

Facebook  Instagram  Bluesky