Broadway & Main Street Safety Improvement Projects: Two-Week Look Ahead

Thank you for your continued interest in the Broadway and Main Street Safety Improvement Projects. We are providing a 2-week look ahead of what work to expect the weeks of June 16 and June 23.

What to Expect: Broadway - Portland Street to Columbia Street

Week of June 16 (Daytime Hours):


This work includes:

  • Converting two resident parking spaces to metered parking in front of the businesses near Clark Street.
  • Converting two meters to a loading zone at Broadway and Moore Street.
  • Converting a loading zone to metered parking across from Davis Street.
  • Adding accessible/disability parking near Fletcher-Maynard Academy.


Week of June 23 (Daytime Hours):

  • We will move the IB bus stop at Windsor Street to its new location across the street.
  • The new stop location will be posted two weeks in advance of the change.
  • MBTA will add an alert of the change to its website.


Future Overnight Work:

  • Pavement markings will be installed either the week of June 23 or June 30, depending on weather and crew availability.

What to Expect: Main Street - Sidney Street to Portland Street

Week of June 16 (Daytime Hours):

  • Milling and Paving:
  • Milling will occur Monday and Tuesday. This is subject to change.
  • Parking changes:
  • Beginning Tuesday, parking will be removed to match the project plans. Click here to view the plans.


Once milling is complete, parking will only be allowed on one side of Main Street.


Week of June 23 (Daytime Hours):

  • Paving work will finish.


Future Overnight Work:

  • Pavement markings will begin the week of June 30, depending on weather and crew availability.
  • Crosswalks will be repainted first, followed by bike lanes and other lane lines.


Final Plans Available

  • Click here to view the final full set of engineering plans.

What to Expect: Main Street - Albany to Technology Square

Upcoming Work

  • We are currently working with our contractor to schedule flex-post installations. The date of this work is unknown, but we will update this email list whenever we have information.

Contact Us


Andreas Wolfe (he/him)

Street Design Project Manager, Department of Transportation

617-349-9162 | awolfe@cambridgema.gov


Leah Grodstein (she/her)

Street Design Project Manager, Department of Transportation

617-349-7202 | lgrodstein@cambridgema.gov

Accessibility Information

The City of Cambridge does not discriminate, including on the basis of disability. We may provide auxiliary aids and services, written materials in alternative formats, and reasonable modifications in policies and procedures to people with disabilities. For more information contact the Department of Transportation at tpt@cambridgema.gov, 617-349-4700 (voice), or via relay at 711.

City of Cambridge

Department of Transportation

Keep in Touch!

Facebook  X  Instagram