Work Completed Week of March 17
Water service installations on the following streets:
- 8400 block of Brookfield Avenue
- 3600 block of Woodside Avenue
In-home assessments on the following streets
- All in-home assessments complete
Pavement/sidewalk restoration on the following streets
- Maple Avenue (Brookfield to Washington)
- 3732 Prairie Ave.
- 3600 block of Woodside Avenue
Temporary pavement restoration on the following streets
Pre-Construction sewer televising on the following streets
- All pre-construction televising is complete
Post-construction sewer televising on various streets
Work to be Completed Next Week
Water service installations on the following streets:
- All water service replacements are complete
In-home assessments on the following streets
- All in-home assessments are complete
Pavement/sidewalk restoration on the following streets
- 3600 block of Woodside Avenue
- 3700-3800 blocks of Raymond Avenue
- 3800 block of Morton Avenue
Temporary pavement restoration on the following streets
Pre-Construction sewer televising on the following streets
- All pre-construction televising is complete
Post-construction sewer televising
- Locations to be determined
|