Work Completed Week of Jan. 20
Water service installations on the following streets:
- Madison Avenue (Shields to Ogden)
- Arthur Avenue (Shields to Ogden)
In-home assessments on the following streets
- Madison Avenue (Shields to Ogden)
- Arthur Avenue (Shields to Ogden)
Pavement/sidewalk restoration on the following streets
Temporary pavement restoration on the following streets
- Madison Avenue (Southview to Washington)
- Arthur Avenue (Shields to Ogden)
Pre-Construction sewer televising on the following streets
Post-construction sewer televising
- Raymond Avenue (Southview to Washington)
- Madison Avenue (Southview to Washington)
Work to be Completed Next Week
Water service installations on the following streets:
- Arthur Avenue (Shields to Ogden)
In-home assessments on the following streets
- Arthur Avenue (Shields to Ogden)
Pavement/sidewalk restoration on the following streets
- Raymond Avenue (Southview to Grant)
Temporary pavement restoration on the following streets
- Madison Avenue (Shields to Ogden)
- Arthur Avenue (Shields to Ogden)
Pre-Construction sewer televising on the following streets
Post-construction sewer televising
- Madison Avenue (Southview to Washington)
|