Brookfield Public Works Responding to Multiple

Water Main Breaks on Village's South End

Brookfield Public Works is currently addressing three separate water main breaks on the south end of the Village:


  • 4100 block of Prairie Avenue
  • 4600 block of Prairie Avenue, near 47th Street
  • Near the intersection of Congress Park and Sunnyside Avenues, in Ehlert Park


Residents affected by these water main breaks have been notified, and water service will be temporarily interrupted when repair work begins until repairs are completed.

RSVP Now to Reserve Your Spot for the Brookfield Aging Well Team's 'Music and Wellness' Event Feb. 24

Discover the power of music and the brain at the Brookfield Aging Well Team's next event, "Music and the Wellness," on Monday, Feb. 24 at 11:45 a.m. at the Brookfield Colgrass Community Cafe, inside the Brookfield Elks Lodge at 9022 31st St. in Brookfield.


The free event includes lunch after the program. RSVP by Feb. 19.

LEARN MORE

Apply for Brookfield Shops 2025 Season

Are you ready to take your budding business to the next level? Applications for The Brookfield Shops of Progress Park are NOW OPEN!


As an emerging business owner, we know how challenging it can be to grow your brand, connect with customers, and test your products in a physical space. That’s why The Brookfield Shops is here to help!


The deadline is Feb. 15. Don’t miss this chance to showcase your talents and grow your business in a supportive environment. Spaces are limited — apply today!

LEARN MORE

Brookfield Chamber of Commerce to Host Valentine Senior Social on Feb. 2 at St. Paul Lutheran Church

The Brookfield Chamber of Commerce invites you to its 2025 Valentine Senior Social on Sunday, Feb. 2 from 1 to 3 p.m. at St. Paul Lutheran Church in Brookfield.


Enjoy lunch, beverages, games, raffles and more! Attendance is limited to 120 people and spots fill up quickly, so reserve yours ASAP.

CLICK HERE FOR THE DETAILS

Brookfield Village Board of Trustees

Meetings on Monday, Jan. 27

The Brookfield Village Board of Trustees will hold its next Regular Business Meeting on Monday, Jan. 27 at 6:30 p.m. The Village Board will conduct its Committee of the Whole Meeting immediately following the Regular Business Meeting.


The meetings will be held in the Council Chamber of the Brookfield Village Hall, 8820 Brookfield Ave.


You can find agendas and minutes for all Brookfield Village Board and Commission meetings on our website by clicking the button below.

AGENDAS AND MINUTES

Village of Brookfield Construction Update for Jan. 24

2024 Lead Water Service Line Replacement Project

In accordance with State statute, the Village of Brookfield will be replacing all of the lead water service lines -- water pipes connecting water mains in the public way to water meters in private properties.


There are about 6,800 water service lines in Brookfield and about one-third of them -- around 2,200 -- are made of lead. Those lead lines will be replaced as part of this capital initiative.


The general contractor performing the work is Five Star Energy Services LLC.



Although these projects cover a large portion of the Village, the contractor typically will only be working on a few select streets/blocks at a time, not all throughout town.


For a map of the 2024 lead water service line replacement project, click here.


OVERALL PROGRESS UPDATE 2024 LEAD WATER SERVICE REPLACEMENTS – PHASES I, II, III


Total Lead Services Replaced to Date:  555 out of 648

Work Completed Week of Jan. 20


Water service installations on the following streets:

  • Madison Avenue (Shields to Ogden)
  • Arthur Avenue (Shields to Ogden)


In-home assessments on the following streets

  • Madison Avenue (Shields to Ogden)
  • Arthur Avenue (Shields to Ogden)


Pavement/sidewalk restoration on the following streets

  • No work (cold weather)


Temporary pavement restoration on the following streets

  • Madison Avenue (Southview to Washington)
  • Arthur Avenue (Shields to Ogden)


Pre-Construction sewer televising on the following streets

  • No work


Post-construction sewer televising

  • Raymond Avenue (Southview to Washington)
  • Madison Avenue (Southview to Washington)




Work to be Completed Next Week


Water service installations on the following streets:

  • Arthur Avenue (Shields to Ogden)


In-home assessments on the following streets

  • Arthur Avenue (Shields to Ogden)


Pavement/sidewalk restoration on the following streets

  • Raymond Avenue (Southview to Grant)


Temporary pavement restoration on the following streets

  • Madison Avenue (Shields to Ogden)
  • Arthur Avenue (Shields to Ogden)


Pre-Construction sewer televising on the following streets

  • No work


Post-construction sewer televising

  • Madison Avenue (Southview to Washington)

Keep up to date on all of our capital improvement projects and find information on who to contact by viewing our GIS map page.