I still have a ton of reverse raffle tickets for August 8th this summer. We will need everyone's help selling (and buying if you're flush enough) these tickets!
100% of what we raise for the next year will go toward making Kenilee Lanes Bowling Center fully wheelchair accessible for our clients and the public at large. We're pretty excited about this project because we think people will be really wowed by the finished design. However, it's a big lift! Our target construction date is May, 2026. This means we have 11 more months to raise $195K.
If you are wondering where all this money will be used. This is our preliminary estimated budget:
Architect or Structural Engineer contract - $6,000
Permits - $3,000
Demolition - $10,000
Rough out interior (restroom + stairway + raise floor) - $70,000
Electrical - $20,000
Plumbing - $15,000
Counter, front kitchen + back galley build out - $25,000
Wheelchair accessible entranceway & facade improvements - $40,000
Misc. - $18,000
Subtotal: $207,000
|