Plano Coudon Construction continues working at 328 N. Howard. On April 30th, project manager Dan Schwab shared the pictures above and reported, "All the interior concrete is now complete, including the in-slab plumbing rough-ins. Today is steel erection, then wood floor framing, once the floor is complete, then we start the interior metal stud wall framing, and exterior demo of the façade."

Onsite meetings, with socially distancing of course, are being scheduled for the week of 5/18. Plans for placement of phones, computers and security will be reviewed. Look for more pictures in our next update.

Please pray for a smooth, uneventful construction process and a GRAND OPENING in the Summer of 2020.

Put Howard St. on every possible prayer list!!