On November 28 to December 4, Caltrain will be working during the night to install equipment on the rail and locate underground utilities. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Caltrain is currently constructing two Paralleling Station facilities in San Francisco. To learn more, please visit our
Resources page.
During work hours at the 22nd St. station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Brisbane On November 28 to December 4, Caltrain will be working during night to install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Caltrain is currently constructing a Paralleling Station facility at the Bayshore Station parking lot. The Bayshore Station will remain open during construction. To learn more, please visit our
Resources page.
During work hours at the Bayshore station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
South San Francisco On November 28 to December 4, Caltrain will be working the day to install conduit. Caltrain will be working during the night to install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the South San Francisco station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
San Bruno On November 28 to December 4, Caltrain will be working the day to install conduit. Caltrain will be working during the night to install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the San Bruno station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Millbrae On November 28 to December 4, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Millbrae station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Burlingame On November 28 to December 4, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Burlingame and Broadway stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
San Mateo On November 28 to December 4, Caltrain will be working during the day to install conduit and to install gantry at the Paralleling Station facility. Caltrain will be working during the night to install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m.
During work hours at the San Mateo and Hayward Park stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287
Belmont On November 28 to December 4, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Belmont station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
San Carlos On November 28 to December 4, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the San Carlos station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Redwood City On November 28 to December 4, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Redwood City station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Unincorporated San Mateo CountyOn November 28 to December 4, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
AthertonOn November 28 to December 4, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Atherton station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Menlo ParkOn November 28 to December 4, Caltrain will be working during the day to locate underground utilities and prune and remove trees along the project route. Caltrain will be working during the night to install poles, install cantilevers and string wire on poles, install foundations, remove abandoned cables, install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Menlo Park station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Palo Alto On November 28 to December 4, Caltrain will be working during the day to install a transformer at the Paralleling Station facility, locate underground utilities and prune and remove trees along the project route. Caltrain will be working during the night to install poles, install cantilevers and string wires on poles, install foundations, remove abandoned cables, install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Caltrain is currently constructing a Paralleling Station facility located near 187 Page Mill Road on Caltrain property in Palo Alto.
From June 9, 2020 to January 2021, crews will utilize a portion of Page Mill Road between Sheridan Avenue and Park Boulevard for construction staging. Vehicles may enter the Caltrain parking lot from Sheridan Avenue, but must exit the parking lot via California Avenue. During construction, crews will use this portion of Page Mill road for intermittent deliveries of equipment and construction supplies to and from the staging area. To learn more, please visit our
Resources page.
During work hours at the Palo Alto and California stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Mountain View On November 28 to December 4, Caltrain will be working during the day to locate underground utilities and prune and remove trees along the project route. Caltrain will be working during the night to install poles, install cantilevers and string wires on poles, remove abandoned cables, install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Mountain View and San Antonio stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Sunnyvale On November 28 to December 4, Caltrain will be working during the day to locate underground utilities and prune and remove trees along the project route. Caltrain will be working during the night to install poles, install cantilevers and string wires on poles, install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Sunnyvale and Lawrence stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Santa Clara On November 28 to December 4, Caltrain will be working during the day to locate underground utilities, and prune and remove trees along the project route. Caltrain will be working during the night to install foundations, string wires on poles, install equipment on the rail, locate underground utilities, and remove abandoned cables. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Caltrain Electrification crews are staging materials and equipment between the Santa Clara Station and the College Park Station in San Jose. Construction staging will occur along the Caltrain right-of-way south of the Santa Clara Station. Caltrain has temporarily closed parking spaces #256-269 and #277-290 at the Santa Clara station for crews to stage equipment. To learn more about staging area construction activities, please visit our
Resources page.
During work hours at the Santa Clara station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
San Jose On November 28 to December 4, Caltrain will be working during the day to install fencing at the Traction Power facilities. Caltrain will be working during the night to install foundations, install equipment on the rail, locate underground utilities and remove abandoned cables. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Between November 30 and December 2, Caltrain will be performing foundation installation work in the median area on Bird Avenue. This road work will require temporary closure of one northbound lane between Hull Avenue and West Virginia Avenue.
On December 3, Caltrain will begin performing Bridge Barrier installation work in San Jose that will require the temporary closure of the eastbound and westbound bicycle lanes of the Hedding Street bridge near Stockton Avenue.
Between the period of December 3 and December 5, Caltrain will be performing foundation installation work on the north side of Willow Street. This road work will require temporary lane shift in the westbound lane starting at Pepitone Avenue.
For more information on the traffic impacts listed above, please visit our
Resources page.
Caltrain Electrification crews are staging materials and equipment between the Santa Clara Station and the College Park Station in San Jose. Construction staging will occur along the Caltrain right-of-way south of the Santa Clara Station. Caltrain has temporarily closed parking spaces #256-269 and #277-290 at the Santa Clara station for crews to stage equipment. To learn more about staging area construction activities, please visit our Resources page.