foundations, perform switch isolations, install equipment on the rail and locate underground utilities. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Caltrain is currently constructing a Paralleling Station facility at the Bayshore Station parking lot. The Bayshore Station will remain open during construction. To learn more, please visit our
Resources page.
During work hours at the 22nd St. station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Brisbane
On August 22 to August 28, Caltrain will be working during night to install foundations, perform switch isolations, install equipment on the rail and locate underground utilities. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Caltrain is currently constructing a Paralleling Station facility at the Bayshore Station parking lot. The Bayshore Station will remain open during construction. To learn more, please visit our
Resources page.
During work hours at the Bayshore station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
South San Francisco
On August 22 to August 28, Caltrain will be working the day to install conduit. Caltrain will be working during the night to perform switch isolations, install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible. During construction motorists and pedestrians may experience intermittent delays while crews move equipment through at-grade crossings.
During work hours at the South San Francisco station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
San Bruno
On August 22 to August 28, Caltrain will be working the day to install conduit. Caltrain will be working during the night to perform switch isolations, install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible. During construction motorists and pedestrians may experience intermittent delays while crews move equipment through at-grade crossings.
During work hours at the San Bruno station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Millbrae
On August 22 to August 28, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to perform switch isolations, install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Millbrae station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Burlingame
On August 22 to August 28, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to perform switch isolations, install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Burlingame and Broadway stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
San Mateo
On August 22 to August 28, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail, perform switch isolations and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m.
During work hours at the San Mateo and Hayward Park stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287
Belmont
On August 22 to August 28, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail, perform switch isolations and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Belmont station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
San Carlos
On August 22 to August 28, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail, perform switch isolations and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the San Carlos station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Redwood City
On August 22 to August 28, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail, perform switch isolations and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Redwood City station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Unincorporated San Mateo County
On August 22 to August 28, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail, perform switch isolations and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Atherton
On August 22 to August 28, Caltrain will be working during the day to install conduit. Caltrain will be working during the night to install equipment on the rail, perform switch isolations and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Crews will be working during the day to install a signal house on Caltrain property near Watkins Avenue. Construction activities include excavation, pouring of concrete and the construction of a new signal house that
will help regulate signaling power to the new electric trains. Work will take place during the weekdays between 7 a.m. and 5 p.m. Limited Saturday work may be required. To learn more, please visit our
Resources page.
During work hours at the Atherton station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Menlo Park
On August 15 to August 21, Caltrain will be working during the day to install foundations, prune and remove trees along the project route and locate underground utilities. Caltrain will be working during the night to string wires on poles, install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Menlo Park station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Palo Alto
On August 22 to August 28, Caltrain will be working during the day to install foundations, prune and remove trees along the project route and locate underground utilities. Caltrain will be working during the night to string wires on poles, install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Caltrain is currently constructing a Paralleling Station facility located near 187 Page Mill Road on Caltrain property in Palo Alto.
From June 9, 2020 to January 2021, crews will utilize a portion of Page Mill Road between Sheridan Avenue and Park Boulevard for construction staging. Vehicles may enter the Caltrain parking lot from Sheridan Avenue, but must exit the parking lot via California Avenue. During construction, crews will use this portion of Page Mill road for intermittent deliveries of equipment and construction supplies to and from the staging area. To learn more, please visit our
Resources page.
During work hours at the Palo Alto and California stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Mountain View
On August 22 to August 28, Caltrain will be working during the day to install foundations, prune and remove trees along the project route and locate underground utilities. Caltrain will be working during the night to string wires on poles, install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Mountain View and San Antonio stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Sunnyvale
On August 22 to August 28, Caltrain will be working during the day to install foundations, prune and remove trees along the project route and locate underground utilities. Caltrain will be working during the night to install poles, string wires on poles, install equipment on the rail and locate underground utilities. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
During work hours at the Sunnyvale and Lawrence stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
Santa Clara
On August 22 to August 28, Caltrain will be working during the day to locate underground utilities and locate underground utilities at the Santa Clara station. Caltrain will be working during the night to install poles, install equipment on the rail, locate underground utilities, and remove abandoned cables. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Caltrain Electrification crews are staging materials and equipment between the Santa Clara Station and the College Park Station in San Jose. Construction staging will occur along the Caltrain right-of-way south of the Santa Clara Station. Caltrain has temporarily closed parking spaces #256-269 and #277-290 at the Santa Clara station for crews to stage equipment. To learn more about staging area construction activities, please visit our
Resources page.
During work hours at the Santa Clara station all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.
San Jose
On August 22 to August 28, Caltrain will be working during the day to locate underground utilities at the Diridon, Tamien and College Park stations. Caltrain will be working during the night to install equipment on the rail, locate underground utilities and remove abandoned cables. Day work hours will be from 7 a.m. to 7 p.m. Night work hours will be from 7 p.m. to 6 a.m. We apologize for any inconvenience this may cause and the field team will work as quietly as possible.
Caltrain Electrification crews are staging materials and equipment between the Santa Clara Station and the College Park Station in San Jose. Construction staging will occur along the Caltrain right-of-way south of the Santa Clara Station. Caltrain has temporarily closed parking spaces #256-269 and #277-290 at the Santa Clara station for crews to stage equipment. To learn more about staging area construction activities, please visit our
Resources page.
During work hours at the Diridon, Tamien and College Park stations all passengers will board and de-board from the same platforms. Please look for the signs to indicate which platform to use. If you have any questions, feel free to call Caltrain Customer Service at 1.800.660.4287.