Big things are brewing for Caltrain, as our new electrified fleet and infrastructure continue to take shape and we come up on a new schedule for the Fall, providing improved service for riders.
This month, our third and fourth electric trainsets made the journey from Utah to California and we were able to run a second clearance test along the full length of our corridor. PG&E has also made power available along Segment 4, which will allow us to activate a 6-mile stretch between Santa Clara and San Jose to begin testing and commissioning the overhead contact system and new electric trains.
Caltrain Electrification will further transform the railroad when the project finishes in 2024 as California’s first electrified commuter rail. The project will provide faster, safer, more frequent service for our customers while enhancing equity and mitigating climate change. We continue to work towards this goal that feels closer day by day.
|