DWM | March 2018
Capital Improvement Program Construction Brief
March 2018
Active Construction
Water Supply Program: Quarry/Chattahoochee/Hemphill

Update: The tunnel boring machine (TBM) is averaging 39 linear feet per working day and is approaching a three mile mark.
Excavation and rebuilding of an existing pump station at the R.M. Clayton Water Reclamation Center, located at 2440 Bolton Road NW continues. Controlled blasting is necessary to complete the shaft and short tunnel for the pump station.
The Water Supply Program will increase Atlanta’s reserve water supply from three to five days to 30 to 90 days. The $300 million investment includes the construction of a five-mile tunnel connecting the Chattahoochee River, the Hemphill Water Treatment Plant and the former Bellwood Quarry, which will be transformed into a 2.4 billion gallon reservoir. The Water Supply Program is scheduled for completion by July 2019.
 
Expected Completion: 7/2019

Project Location: Northwest Atlanta

Council District(s): 3, 9

Neighborhood Planning Unit(s): C, D, G, J, K 

Upper Proctor Creek Capacity Relief Project:
Rodney Cook Sr. Park in Historic Vine City
Update: Contractors are performing soil remediation work on the Cook Park site. Crews are also decommissioning water lines requiring temporary water service interruptions on neighboring streets.

The project is designed to help alleviate flooding while providing increased greenspace in Vine City. The project consists of installing a new capacity relief storage facility in the area, installing 2,200 linear feet of 60-inch capacity relief trunk line, re-routing 1,100 LF of 96-inch combined trunk sewer by installing pipeline in the right-of-way along street in the Vine City area and remediating and relocating sewers. 

Expected Completion: 12/2018
Project Location: Northwest Atlanta
Council District(s): 3
Neighborhood Planning Unit(s): L 

R.M. Clayton Sand Filter Media Installation and Refurbishment Project
Sixty percent of the R.M. Clayton Water Reclamation (WRC)and Filter Media Change-out and Refurbishment Project is complete with new media installed. Seventy-two percent of all media has been removed. Eighty percent of all media to complete the refurbishment is onsite. Air pattern testing is underway and is expected to be completed by the first week of March. At least 14 of 22 filter replacements are complete.
 
The R.M. Clayton WRC treatment process removes biological and chemical impurities from the wastewater in three phases: primary treatment, secondary treatment and tertiary treatment. Primary sludge and biological solids that are removed during the wastewater treatment process are reduced in the digestion process before being dewatered and incinerated or hauled to a landfill. This project will restore the effectiveness of the filtration process, reduce the backwash frequency and duration, reduce the maintenance costs and improve overall plant reliability in meeting permit limits. The project is estimated to be completed in June 2018.
 
Expected Completion: 6/2018
Project Location: R. M. Clayton Water Reclamation Center
Council District(s): 9
Neighborhood Planning Unit(s): D

Upper Proctor Creek Boone Boulevard Green Infrastructure

Update: Stormwater planter boxes, sidewalks, driveway aprons and tree installations have been completed along the southern side of Joseph E. Boone Boulevard NW between Joseph E. Lowery Boulevard NW and Sunset Avenue NW. Now, DWM will replace water mains on Joseph E. Boone Boulevard NW between Northside Drive NW and Mayson Turner Road NW. Water main replacement work is tentatively scheduled for the first quarter of 2018.

Expected Completion: 12/2018
Project Location: Northwest Atlanta
Council District(s): 3
Neighborhood Planning Unit(s): K, L, M 

Cascade Road Water Main Installation
Update: Crews are currently connecting water service lines to the new water main.
In addition, eight-inch water main installation work continues on Cascade Road SW between Childress Drive SW and Beecher Street SW, resulting in a temporary westbound lane closure. 

Expected Completion: 03/2018
Project Location: Southwest Atlanta
Council District(s): 4
Neighborhood Planning Unit(s): S 

Peachtree Battle Avenue Water Main Installation
Update: Crews are connecting water service lines to the new water main. 
In addition, eight-inch water main installation work continues on Peachtree Battle Avenue NW between Bohler Road NW and Northside Drive NW, resulting in a temporary eastbound lane closure.

Expected Completion: 3/2018
Project Location: Northwest Atlanta
Council District(s): 8
Neighborhood Planning Unit(s): B, C

Neighborhood Planning Unit (NPU)

The City of Atlanta is divided into 25 Neighborhood Planning Units (NPU), which serve as citizen advisory councils that make recommendations to the Mayor and City Council on zoning, land use, and other planning issues. NPUs also allow citizens to receive information about all functions of city government.  

See Neighborhoods Located within Listed NPUs Below: 

NPU-B 

  • Brookhaven
  • Buckhead Forest
  • Buckhead Village
  • East Chastain Park
  • Garden Hills
  • Lenox
  • Lindbergh/Morosgo
  • North Buckhead
  • Peachtree Heights East and West
  • Peachtree Hills
  • Peachtree Park
  • Pine Hills
  • Ridgedale Park 
  • South Tuxedo Park

NPU-C 

  • Arden/Habersham
  • Argonne Forest
  • Brandon
  • Castewood
  • Channing Valley
  • Collier Hills
  • Collier Hills North
  • Colonial Homes
  • Cross Creek
  • Fernleaf
  • Hanover West
  • Memorial Park
  • Peachtree Battle Alliance
  • Ridgewood Heights
  • Springlake
  • Wesley Battlle
  • Westminister/Milar
  • Westover Plantation
  • Wildwood
  • Woodfield
  • Wyngate

NPU-D

  • Berkley Park
  • Blandtown
  • Bolton
  • Hills Park
  • Riverside
  • Underwood Hills
  • Whittier Mill Village
 
NPU-G

  • Almond Park
  • Atlanta Industrial Park
  • Bolton Hills
  • Brookview Heights
  • Carey Park
  • Carver Hills
  • Chattahoochee
  • English Park
  • Lincoln Homes
  • Monroe Heights
  • Rockdale
  • Scotts Crossing
  • West Highlands

NPU-J

  • Center Hill
  • Dixie Hills
  • Grove Park
  • Harvel Homes
  • Penelope Neighbors
  • West Lake

NPU-K

  • Bankhead
  • Hunter Hills
  • Knight Park/Howell Station
  • Mozley Park
  • Washington Park

NPU-L

  • English Avenue
  • Vine City

NPU-M 

  • Castleberry Hill
  • Downtown
  • Old Fourth Ward

NPU-P

  • Arlington Estates
  • Ashley Courts
  • Ben Hill
  • Brentwood
  • Briar Glen
  • Butner/Tell
  • Cascade Green
  • Deerwood
  • Fairburn
  • Greenbriar Village
  • Heritage Valley
  • Huntington
  • Kings Forest
  • Lake Estates
  • Meadowbrook Forest
  • Mellwood 
  • Mt. Gilead Woods
  • Niskey Cove
  • Niskey Lake
  • Princeton Lakes
  • Wildwood Forest

NPU-S 

  • Bush Mountain
  • Cascade Avenue/Road
  • Fort McPherson
  • Oakland City
  • Venetian Hills
  • Westmont Estates

For more information about Watershed Management's Capital Improvement Program, visit http://www.atlantawatershed.org/cip/.