Update:
The tunnel boring machine (TBM) is averaging 39 linear feet per working day and is approaching a three mile mark.
Excavation and rebuilding of
an existing pump station at the R.M. Clayton Water Reclamation Center, located at 2440 Bolton Road NW continues. Controlled blasting is necessary to complete the shaft and short tunnel
for the pump station.
The Water Supply Program will increase Atlanta’s reserve water supply from three to five days to 30 to 90 days. The $300 million investment includes the construction of a five-mile tunnel connecting the Chattahoochee River, the Hemphill Water Treatment Plant and the former Bellwood Quarry, which will be transformed into a 2.4 billion gallon reservoir. The Water Supply Program is scheduled for completion by July 2019.
Expected Completion: 7/2019
Project Location: Northwest Atlanta
Council District(s): 3, 9