Water Supply Program
Quarry/Chattahoochee/Hemphill
|
|
Update:
The 400-foot-long tunnel boring machine (TBM) known as “Driller Mike” has completed the 5-mile journey to the R.M. Clayton Water Reclamation Center located at 2440 Bolton Road NW. Next, DWM will line the interior of the tunnel with concrete and continue the construction of two new pump stations at the Bellwood Quarry and the Hemphill Water Treatment Plant sites.
In addition, DWM will begin controlled blasting at the Hemphill Water Treatment Plant.
The Water Supply Program will increase Atlanta’s reserve water supply from three to five days to 30 to 90 days. The $300 million investment includes the construction of a five-mile tunnel connecting the Chattahoochee River, the Hemphill Water Treatment Plant, and the former Bellwood Quarry, which will be transformed into a 2.4 billion gallon reservoir. The Water Supply Program is scheduled for completion by September 2019.
Expected Completion:
September 2019
Project Location:
Northwest Atlanta
Council District(s):
3, 9
Neighborhood Planning Unit(s):
C, D, G, J, K
|
|
Clear Creek West Sewer Improvements Project
Civic Center Vault
|
|
Update:
Construction phase has actively resumed. The project is currently ongoing.
The City of Atlanta's Department of Watershed Management has identified the need for an underground storage vault to be installed to increase the storage capacity of the existing combined sewer system in the Clear Creek West basin. The vault associated with this project is located in the southeastern corner of the existing Civic Center parking lot adjacent to Ralph McGill Boulevard. The Butler Street trunk and relief combined sewers drain the upper section of the west Clear Creek basin. During certain rainfall events this system can become surcharged, which may result in flooding. The storage vault will store excess combined sewer flows from the Butler Street Relief Combined Sewer, which intercepts at the I-75/85 entrance ramp from Freedom Parkway and Highland Avenue. Stored combined sewer flow in the vault will reduce the peak flow in the downstream combined sewer helping to reduce flooding.
This stormwater vault will help manage rainfall runoff from the adjacent federal highways and downtown portions of the basin. Additionally, implementation of green infrastructure projects are proposed to further manage combined sewer peak flows to the combined sewer system and to reduce the required capacities of the vaults.
Expected Completion:
March 2019
Project Location:
Northeast Atlanta
Council District(s):
2
Neighborhood Planning Unit(s):
M, E
|
|
Upper Proctor Creek Capacity Relief Project
Rodney Cook Sr. Park In Historic Vine City
|
|
Update:
Replacement of the sewer line from Walnut to Thurmond Street is complete. Joint testing and water proofing is completed.
The project is designed to help alleviate flooding while providing increased greenspace in Vine City. The project consists of installing a new capacity relief storage facility in the area, installing 2,200 linear feet of 60-inch capacity relief trunk line, re-routing 1,100 LF of 96-inch combined trunk sewer by installing pipeline in the right-of-way along streets in the Vine City area and remediating and relocating sewers.
Expected Completion:
November 2018
Project Location:
Vine Street NW
Council District(s):
3
Neighborhood Planning Unit(s):
C, D, E, G, H, I, J, K, L, M T
|
|
Boone Boulevard Green Infrastructure & Capacity Relief Project
|
|
Update
: Water main replacement work will continue on Joseph E. Boone Boulevard NW between Elm Street NW and Northside Drive NW.
Stormwater planter boxes, sidewalks, driveway aprons and tree installations have been completed along the southern side of Joseph E. Boone Boulevard NW between Joseph E. Lowery Boulevard NW and Sunset Avenue NW. Also, under the scope of the project, DWM will replace water mains on Joseph E. Boone Boulevard NW between Northside Drive NW and Mayson Turner Road NW.
Expected Completion:
June 2019
Project Location:
Northwest Atlanta
Council District(s):
3
Neighborhood Planning Unit(s):
K, L, M
|
|
Energy Services Performance Initiatives
Noresco/Schneider
|
|
Update:
Contractors will start lighting work at the 14th Street Administration Complex, changing over from conventional to LED lighting. At South River WRC, contractors continue the cleanout of digester #5. Roofing repair is in the final stages of completion at Utoy Creek.
Facilities infrastructure improvements continue at the RM Clayton WRC, Hemphill water distribution system, South River WRC, Utoy Creek WRC, Chattahoochee Water Treatment and 14th Street Administration Complex.
Expected Completion:
December 2020
Project Location:
RM Clayton WRC, Hemphill WTP (Settled Solids only), South River WRC, Utoy Creek WRC, Chattahoochee Water Treatment, and 14th St Admin Complex
Council District(s):
1,3,8,9,10,
Neighborhood Planning Unit(s):
C,D,E,G,H,Z
|
|
RM Clayton Nutrient Recovery – Ostara
|
|
Update
: Contractors will continue micropiling at RM Clayton WRC to form foundation for Nutrient Recovery building.
The purpose of this project is to improve nutrient (phosphorus and nitrogen) removal within the RM Clayton WRC. Enhanced nutrient removal will improve permit compliance, reduce chemical and operating costs, and provide a reusable byproduct.
Expected Completion:
TBD
Project Location:
RM Clayton WRC
Council District(s):
2, 3, 4, 5, 6, 7, 8, 9
Neighborhood Planning Unit(s):
A, B, C, D, E, F, G, J, K, L, M, O, S, T, V
|
|
Proctor Creek Sewer Basin
Ashby-Jett Sewer Improvement Project
|
|
Update:
The Purpose of this project is to upsize the existing Ashby-Jett outfall from 18-inches to 30-inches. The City of Atlanta modeling group proposed upsizing the outfall to provide capacity relief and reduce the surcharge in the existing trunk line. The project includes upsizing the existing line by excavating down to, and exposing the existing pipe in an open cut trench so that the pipe can be repaired or replaced. The trench is then backfilled to close it. The existing line is west of the CSX railroad where the fallout discharges into the Proctor Creek Trunk.
Sewer work is completed. Trees will be planted this Fall.
Expected Completion:
November 2018
Project Location(s):
Bankhead, Hills Park, Center Hill, Grove Park, Washington Park, Hunter Hills Knight Park
Council District(s):
3
Neighborhood Planning Unit(s):
L, K
|
|
Peachtree Creek Sewer Basin
Peachtree Creek Trunk Stabilization
|
|
Update:
The City of Atlanta is continuing its implementation of a comprehensive program to upgrade its existing sanitary sewer system to eliminate wet weather sewer overflows. To accomplish this, the Peachtree Creek Trunk sewer, which traverses through Atlanta Memorial Park and neighboring Bobby Jones Golf Course will be rehabilitated by installation of an interlocking grouted PVC profile structural liner as a permanent solution to ensure the long-term structural integrity and service life of the sewer, an existing 96-inch arch shape concrete pipe. The winding machine rotates and traverses within the pipe, interlocking the PVC profile together against the host pipe wall. The process requires only a manhole or existing access chambers for rehabilitation.
The start of the lining process is underway utilizing the new Spiral Wound technology. Spiral Wound is an innovative technology for rehabilitating pipelines without digging, producing a tight fitting line with no grout required.
Expected Completion:
September 2019
Project Locations(s):
Atlanta Memorial Park, Brandon, Cross Creek, DeFoors Ferry, Hanover West, Peachtree Battle, Ridgewood Heights, Wesley Battle, Westover Plantation, Wildwood, Woodfield
Council District(s):
8, 9
Neighborhood Planning Unit(s):
C, D
|
|
Neighborhood Planning Unit (NPU)
The City of Atlanta is divided into 25 Neighborhood Planning Units (NPU), which serve as citizen advisory councils that make recommendations to the Mayor and City Council on zoning, land use, and other planning issues. NPUs also allow citizens to receive information about all functions of city government.
|
|
See neighborhoods located within listed NPUs below:
|
|
NPU-B
- Brookhaven
- Buckhead Forest
- Buckhead Village
- East Chastain Park
- Garden Hills
- Lenox
- Lindbergh/Morosgo
- North Buckhead
- Peachtree Heights East and West
- Peachtree Hills
- Peachtree Park
- Pine Hills
- Ridgedale Park
- South Tuxedo Park
NPU-C
- Arden/Habersham
- Argonne Forest
- Brandon
- Castewood
- Channing Valley
- Collier Hills
- Collier Hills North
- Colonial Homes
- Cross Creek
- Fernleaf
- Hanover West
- Memorial Park
- Peachtree Battle Alliance
- Ridgewood Heights
- Springlake
- Wesley Battlle
- Westminister/Milar
- Westover Plantation
- Wildwood
- Woodfield
- Wyngate
NPU-D
- Berkley Park
- Blandtown
- Bolton
- Hills Park
- Riverside
- Underwood Hills
- Whittier Mill Village
NPU-G
- Almond Park
- Atlanta Industrial Park
- Bolton Hills
- Brookview Heights
- Carey Park
- Carver Hills
- Chattahoochee
- English Park
- Lincoln Homes
- Monroe Heights
- Rockdale
- Scotts Crossing
- West Highlands
|
|
NPU-J
- Center Hill
- Dixie Hills
- Grove Park
- Harvel Homes
- Penelope Neighbors
- West Lake
NPU-K
- Bankhead
- Hunter Hills
- Knight Park/Howell Station
- Mozley Park
- Washington Park
NPU-L
NPU-M
- Castleberry Hill
- Downtown
- Old Fourth Ward
NPU-O
- East Lake
- Edgewood
- Kirkwood
- The Villages at East Lake
NPU-P
- Arlington Estates
- Ashley Courts
- Ben Hill
- Brentwood
- Briar Glen
- Butner/Tell
- Cascade Green
- Deerwood
- Fairburn
- Greenbriar Village
- Heritage Valley
- Huntington
- Kings Forest
- Lake Estates
- Meadowbrook Forest
- Mellwood
- Mt. Gilead Woods
- Niskey Cove
- Niskey Lake
- Princeton Lakes
- Wildwood Forest
NPU-S
- Bush Mountain
- Cascade Avenue/Road
- Fort McPherson
- Oakland City
- Venetian Hills
- Westmont Estates
|
|
Department of Watershed Management
72 Marietta Street NW
Atlanta, GA 30303
|
|
|
|
|
|
|