CONSTRUCTION ACTIVITIES:
Crews will continue excavating along Lakeside Avenue between Pine Street and the westerly driveway of 128 Lakeside Avenue (the Innovation Center) to facilitate the installation of underground utilities (waterline, electrical vaults, conduit, duct bank, and stormwater infrastructure) and the reconstruction of the roadway. This work will be completed under the full closure of Lakeside Avenue within the project limits.
On Wednesday, July 26, between the hours of 4:00 a.m. and 7:00 p.m., crews will be completing waterline work at the intersection of Pine Street and Lakeside Avenue. This work will be completed under traffic shifts with the potential for a single closure. There are no water service interruptions anticipated as part of this work.
There is the potential for fine grading and paving activities along Flynn Avenue between Foster Street and just west of the railroad crossing. This work will be completed under intermittent single-lane closures.
There is the potential for crews to grade the sidewalk and sections of shared-use path along Home Avenue. This work may require single-lane closures.
Traffic signal equipment will be installed on Sears Lane at its intersection with the Champlain Parkway. This work will require minimal impacts to traffic.
Crews will complete additional work outside of the roadway throughout the project area. Crews will continue installing conduit and junction boxes along the Champlain Parkway alignment between Home Avenue and Lakeside Avenue.
|