CONSTRUCTION ACTIVITIES:
Please note that paving operations and curb installation are subject to weather and subcontractor availability. Construction activities along the east and west sides of Pine Street will be staged to provide an appropriate distance between work zones to allow for the maintenance of traffic along the entire length of Pine Street.
Work will continue along Lakeside Avenue between Pine Street and the westerly driveway of 128 Lakeside Avenue (the Innovation Center) as crews continue reconstructing the roadway. Crews will begin installing sidewalk along the south side and shared-use path along the north side. Crews will complete any remaining conduit and duct bank work along Lakeside Avenue.
Work continues along Pine Street between Kilburn Street and Lakeside Avenue. Crews will be paving the shared-use path along the west side on Friday, September 22, and Saturday, September 23. During the week, crews will continue prepping for the installation of the curb along the west side of Pine Street working toward Lakeside Avenue. Another crew will follow behind to topsoil and clean up along the newly installed curb and shared-use path. There is the potential for crews to begin prepping for the installation of curb along the east side of Pine Street starting at Kilburn Street and working toward Lakeside Ave. Crews will continue installing and rehabilitating drainage infrastructure along Pine Street.
Crews will install sidewalk along portions of Flynn Avenue between Foster Street and the railroad crossing.
Crews will be paving residential driveways along Lyman Avenue, Ferguson Avenue, Home Avenue, and Batchelder Street on Friday, September 22.
Early next week, crews will install curb along portions of the Champlain Parkway between Home and Lakeside Avenues. This work will take place off the roadway. There is the potential for crews to start installing curb along Lakeside Avenue between Pine Street and the westerly driveway of 128 Lakeside Avenue (the Innovation Center).
|