CONSTRUCTION ACTIVITIES, DURATION, AND TRAFFIC IMPACTS:
Crews will be on-site Monday, July 11, through Friday, July 15, between the hours of 7:00 a.m. and 7:00 p.m. Monday and Tuesday, crews will complete clearing and grubbing activities along the project Right of Way between Lakeside and Flynn Avenues. Throughout the week, crews will continue clearing work along Briggs and Batchelder Streets. Clearing activities will require parking restrictions along Briggs Street and the west side of Batchelder Street as posted.
Preparatory work for the installation of the stormwater sand filter located off the roadway just west of the Champlain College Miller Building on Lakeside Avenue will begin. This work includes grubbing the area, stripping the topsoil for future use, and excavating. In addition, crews will be removing the pavement within the project Right of Way along the east side of the parking area between Lakeside Avenue and Sears Lane in preparation for the installation of additional stormwater infrastructure in the area leading to the sand filter.
Crews will complete the construction of the stream bypass for Englesby Brook to facilitate future culvert work. Crews will also work to complete ground improvements in the area. This work will be completed off the roadway in the wooded area to the west of Pine Street between Sears Lane and Flynn Avenue.
|