Construction Update

Champlain Parkway Project

DATE: Friday, December 20, 2024

SPECIAL NOTICE:

Crews may be onsite Monday, December 23, to install variable message signs in various locations in Burlington in advance of construction starting for the final contract of the Champlain Parkway. These signs will provide motorists with an advanced warning of construction impacts. Regular construction activities are anticipated to begin on Monday, December 30, throughout the project area. 

DURATION:

Construction activities are anticipated to take place starting Monday, December 30, through Friday, January 3, between the hours of 7 a.m. and 7 p.m.



In observance of New Year’s Day, no construction activities will take place on Wednesday, January 1. Crews will be offsite by 7 p.m. on Tuesday, December 31, and return on Thursday, January 2, at 7 a.m.

CONSTRUCTION ACTIVITIES & TRAFFIC IMPACTS:

On Monday, December 23, crews may be onsite installing variable message signs in various locations in Burlington. Starting Monday, December 30, crews are anticipated to begin installing construction signage along portions of I-189, Route 7, Pine Street, and Queen City Park Road. These activities may require temporary single-lane or shoulder closures. Traffic will be maintained.



In addition, crews are anticipated to begin to mobilize materials and equipment to the stockpile and staging areas located on Sears Lane (west of the Champlain Parkway) and the unused section of the previously constructed Southern Connector (just west of Route 7). There is the potential for crews to begin clearing vegetation and setting up erosion protection and sediment control measures along the unused section of the Southern Connector between I-189 and Home Avenue. These activities will take place off the roadway with limited impacts to traffic. 

INITIAL CONTRACT UPDATE:

As part of the initial contract, East Coast Signals will be onsite intermittently throughout December to complete the remaining traffic signal work. East Coast Signals will complete the remaining adjustments to the timing and phasing at the intersections of the Champlain Parkway at Home Avenue, Flynn Avenue, Sears Lane, and Lakeside Avenue, and Pine Street at Lakeside Avenue, to address observations made since the new roadway was opened to traffic. This work will take place between the hours of 7 a.m. and 7 p.m. with limited impact on traffic.

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract includes the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street. 



The final contract includes the construction of the Champlain Parkway from existing I-189 near its intersection with U.S. Route 7 to Home Avenue, and the section of Pine Street between Kilburn Street and Main Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2026

NEARBY CONSTRUCTION PROJECT ALERT:

Construction vehicles and other equipment will be traveling throughout the South End as part of the Burlington Great Streets: Main Street Project, which began construction in February. A staging area for this project (where construction materials and equipment are stored) is located on Sears Lane. In addition, this project will be detouring traffic through the Champlain Parkway project limits.


This project, which is separate from the Champlain Parkway Project, encompasses the portion of Main Street between Battery Street and South Union Street. For additional information or to sign up to receive their project updates, visit the Burlington Great Streets project website