Champlain Parkway Project

DATE: Friday, January 30, 2026

SPECIAL NOTICE:

Construction activities are significantly reduced during the winter shutdown period.


This will be the last Construction Update until construction activities resume in March 2026. Regular weekly Construction Updates will begin in advance of the crews' return to the site. 

CHAMPLAIN PARKWAY & MAIN STREET GREAT STREETS HIGHLIGHTS:

The Burlington Department of Public Works maintains a construction map containing traffic impacts, including traffic restrictions, roadway closures, and more, for all major construction projects in the Downtown District and the South End. Plan your travel with the most up-to-date information by using the map here.

Traffic impact highlights for the Champlain Parkway Project for Monday, February 2, through Friday, February 6, are listed below:

  • Pine Street – Kilburn Street to Maple Street: Potential for lane closures or shifts facilitate the relocation of the pedestrian crossing beacons. This work is anticipated to be completed in one day.
  • Future Champlain Parkway – I-189 to Home Avenue: Fully closed, all traffic strictly prohibited.


For more detailed information on construction activities and traffic impacts related to the Champlain Parkway Project, read the Construction Update section below.

Traffic impact highlights for the Main Street – Great Streets Project for Monday, February 2, through Friday, February 6, are listed below:

  • The Main St. corridor is open for the winter to through-traffic.
  • While some pedestrian detours may be in place, pedestrian access is maintained throughout the entire project area unless otherwise noted.
  • Main: S. Winooski-St. Paul: New traffic signals have been installed and are active. Please note that signals are either in four-way red flash or a test period (standard protocol for all new signal installations), and will be closely monitored over the next few weeks. Signals currently in flash (Main/Church, Main/St Paul) will be operating within the next few weeks.


For additional information on the Great Streets – Main Street Project or to view the latest construction updates and traffic impacts, visit the project website by using the link here.

Adjacent Project Impact:

  • S. Winooski Avenue: Main Street - King Street: Unrelated project work from a private developer will limit travel to southbound traffic only. This pattern will be in place until further notice.

DURATION:

Unless otherwise noted, work will be restricted to the hours of 7 AM and 7 PM, Monday through Friday.

CONSTRUCTION ACTIVITIES & TRAFFIC IMPACTS:

Pine Street (north) - Main Street to Kilburn Street:

Crews will be relocating pedestrian crossing beacons along Pine Street between Kilburn Street and Maple Street. This work may require lane closures and shifts and will be completed in one day. Flaggers will be present to assist motorists through the work zone.



Off the Roadway along the Future Champlain Parkway Alignment:

Please note that the streetlights are currently turned on as part of a testing phase. The lights will be turned off again once testing is complete in a few weeks.

The segment of the Champlain Parkway between Interstate 189 and Home Avenue is not completed and is not open for public access. Active construction continues along this segment, which includes the movement and transport of construction vehicles, equipment, and materials. All other access (vehicular, pedestrian, or bicycle) is strictly prohibited.

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract, conditionally accepted in December 2024, included the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street.



The final contract, which broke ground in January 2025, includes the construction of the Champlain Parkway from existing I-189 near its intersection with U.S. Route 7 to Home Avenue and the section of Pine Street between Kilburn Street and Main Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2026

CONTACT US:

For more information about the project, please visit the project website champlainparkway.com, or contact the project team via the project hotline, 802-496-8956, or by email: info@champlainparkway.com.