Construction Update

Champlain Parkway Project

DATE: Friday, April 7, 2023

SPECIAL ANNOUNCEMENTS:

The Champlain Parkway Project, which remains in winter shutdown, is anticipated to begin mobilizing on April 10 with construction activities anticipated to resume on April 17. A supplemental notice regarding the planned construction activities for the 2023 construction season will follow. 


TRAFFIC IMPACTS: 

No impacts to traffic are anticipated however, construction vehicles may be parked on the road shoulders in advance of and throughout the work zone while crews install signage.


CONSTRUCTION ACTIVITIES:

Monday, April 10, and Tuesday, April 11, crews will be on-site installing construction signage and message boards.


There is the potential for a crew to begin DigSafe utility markings along Home Avenue, Flynn Avenue, Batchelder Street and Sears Lane next week.


Independent utility companies may be in the project area relocating aerial utilities throughout the week. 



CWSRF Pump Station Replacement Project

Burlington Water Resources is conducting work along Flynn Avenue related to the CWSRF Pump Station Replacement Project that began the week of March 20th. This work is being completed during the daytime hours under single-lane closures with alternating east-west traffic along Flynn Avenue starting west of the intersection with Briggs Street. The roadway is anticipated to reopen each evening. No driveway impacts are anticipated to the businesses between Briggs Street and the railroad crossing.

 

This work is independent of the Champlain Parkway Project. For more information about the CWSRF Pump Station Replacement Project, please contact Ashley Walenty, Project Manager, Burlington Water Resource Department, awalenty@burlingtonvt.gov or Robert Goulding, Public Information Manager, Burlington Department of Public Works, rgoulding@burlingtonvt.gov or call Burlington Water Resources at 802-863-4501.

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract includes the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2027

Project Website

CONTACT US:

For more information about the project please visit the project website champlainparkway.com or contact the project team via the project hotline, 802-496-8956 or by email: info@champlainparkway.com.

Facebook  Twitter