Construction Update

Champlain Parkway Project

DATE: Friday, March 31, 2023

SPECIAL ANNOUNCEMENTS:

The Champlain Parkway Project, which remains in winter shutdown, is anticipated to begin mobilizing on April 10 with construction activities anticipated to resume on April 17. A supplemental notice regarding the planned construction activities for the 2023-2024 construction season will follow. 


INDEPENDENT UTILITY UPDATE:  

Monday, April 3, and Tuesday, April 4, Burlington Electric Department (BED) will be onsite installing a new utility pole and relocating an existing guywire in preparation for future culvert work. This work will be completed on Home Avenue near the railroad crossing and will require intermittent lane closures with alternating one-way traffic. Flaggers will be present. No service interruptions are anticipated as part of this work.


There is the potential for Consolidated Communications to be onsite next week to install a new utility pole on Home Avenue just east of the railroad crossing, near the entrance to the bike path.

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract includes the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2027

Project Website

CONTACT US:

For more information about the project please visit the project website champlainparkway.com or contact the project team via the project hotline, 802-496-8956 or by email: info@champlainparkway.com.