|
CONSTRUCTION ACTIVITIES:
Crews will continue excavating along Lakeside Avenue between Pine Street and the westerly driveway of 128 Lakeside Avenue (the Innovation Center) to facilitate the installation of duct bank and the reconstruction of the roadway. This work will be completed under the full closure of Lakeside Avenue within the project limits.
Crews will be installing duct bank along Pine Street in the vicinity of its intersection with Lakeside Avenue. This work will require lane shifts to maintain two lanes of traffic along Pine Street in the vicinity. There is the potential this work may require a single-lane closure with alternating one-way traffic.
Crews will continue constructing the shared-use path and prepping for the installation of curb along the west side of Pine Street between Kilburn Street and Lakeside Avenue. Crews will begin at Kilburn Street and continue south. This work will require the excavation of the area just west of the shared-use path and just east of the edge of pavement along the west side of Pine Street. Crews will backfill the area as they progress south. This work will take place predominantly off the roadway; however, it may require shoulder closures along Pine Street. This work will impact driveways. Impacted property owners and tenants will be notified. Access and egress will be maintained throughout the work.
Crews will continue conducting investigatory work along the east side of Pine Street between Lakeside Avenue and Kilburn Street in preparation for upcoming work in that area. Crews will begin installing stormwater infrastructure along the west side of Pine Street. This work will require lane shifts or lane reductions with alternating one-way traffic along Pine Street.
Crews will be fine-grading and paving Flynn Avenue west of the railroad crossing. This work will require single-lane reductions. Paving operations are weather dependent.
East Coast Signals will be on-site throughout the week conducting work on the traffic signals at the railroad crossings with limited impact to traffic. There is the potential for East Coast Signals to work on the traffic signal at the intersection of Lakeside Avenue and the Champlain Parkway. This work would take place within the closure area.
Crews will complete additional work outside of the roadway throughout the project area. Crews will be fine-grading the shared-use path in preparation for paving and will continue installing fencing along the Champlain Parkway between Home Avenue and Lakeside Avenue.
|