Construction Update

Champlain Parkway Project

DATE: Friday, July 7, 2023

SPECIAL ANNOUNCEMENTS: 

Starting Monday, July 10, at 7:00 a.m. Lakeside Avenue between Pine Street and the westerly driveway of 128 Lakeside Avenue (the Innovation Center) will close for up to six weeks. The closure will be in place 24 hours a day, 7 days a week.  For additional information regarding the work at Lakeside Avenue, click here.


Starting Monday, July 10, at 6:30 p.m. through Tuesday, July 11, at 6:30 a.m., crews will be conducting night work at the intersection of Pine Street and Lakeside Avenue. Pine Street will be reduced to a single lane with alternating one-way traffic. Lakeside Avenue will be closed at its intersection with Pine Street (see above). Flaggers will be present to assist motorists through the work zone. This work is weather dependent. 

TRAFFIC IMPACTS: 

Unless otherwise noted, work will be restricted to between the hours of 7:00 a.m. to 7:00 p.m., all roadway and lane closures will reopen during the evening hours and on weekends, and access to residential and business driveways will be maintained. Flaggers will be present to assist motorists throughout the work zone. Businesses will remain open! Motorists should anticipate rough and uneven gravel driving surfaces throughout the work zone.


Throughout the week, Flynn Avenue will be reduced to a single lane with alternating one-way traffic between Briggs Street and the railroad crossing to facilitate roadway reconstruction. In addition, the City of Burlington is paving the section of Flynn Avenue starting west of the railroad crossing and continuing to Oak Beach Drive. This work is anticipated to be completed in mid-July. Inquiries on the Flynn Avenue Paving can be directed to the Department of Public Works at 802-863-9094 or dpw-pinestreetcustomerservice@burlingtonvt.gov.


CONSTRUCTION ACTIVITIES:

Crews will continue excavating along Lakeside Avenue between Pine Street and the westerly driveway of 128 Lakeside Avenue (the Innovation Center) to facilitate the installation of underground utilities (waterline, electrical vaults, and ductbank) and the reconstruction of the roadway. Crews will also be installing traffic signal bases at the intersection of Lakeside Avenue and the Parkway alignment. This work will be completed under the full closure of Lakeside Avenue within the project limits.


Crews will be installing waterline within the intersection of Lakeside Avenue and Pine Street between the nighttime hours of 6:30 p.m. and 6:30 a.m. starting Monday, June 10 at 6:30 p.m. This work will be completed under the full closure of Lakeside Avenue and single-lane closures with one-way alternating traffic along Pine Street.


Crews will continue reconstructing Flynn Avenue between Briggs Street and the railroad crossing. Crews will excavate sections of Flynn Avenue for reconstruction under single-lane closures. Motorists should expect a gravel surface along portions of Flynn Avenue throughout the week. This may require short driveway closures along Flynn Avenue. Alternative access to businesses will be provided as needed.


Work will continue constructing the cul-de-sacs at the west end of Ferguson and Lyman Avenues and the south end of Briggs Street as crews install curb. This work may require short driveway closures. Impacted property owners and residents will be notified by a member of the Project Team.


Traffic signal bases will be installed on Sears Lane at its intersection with the Champlain Parkway. This work will require minimal impacts to traffic.



Crews will complete additional work outside of the roadway throughout the project area. Crews will begin grading the bike path along the Parkway alignment between Home Avenue and Lakeside Avenue. 

NOTICE OF TEMPORARY SUSPENSION OF QUIET ZONE: Work continues on the rail road crossing improvements at Flynn and Home Avenues. A temporary suspension of the residential Quiet Zone will be in effect to facilitate the improvement work. Audible train horns will be used to provide advanced warning of oncoming trains. The residential Quiet Zone will be reestablished once the work is completed.

PUBLIC SAFETY ANNOUNCEMENT: For your safety and the safety of the construction crew and field staff, the Champlain Parkway Project Team reminds the public to steer clear of construction vehicles, heavy machinery, and active construction areas. Stay alert when navigating within the work zone. For all urgent issues or concerns, please contact the Public Outreach Team by phone at (802)496-8956 or by email at info@champlainparkway.com.

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract includes the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2027

Project Website

CONTACT US:

For more information about the project please visit the project website champlainparkway.com or contact the project team via the project hotline, 802-496-8956 or by email: info@champlainparkway.com.

Facebook  Twitter