|
Pine Street (north) Main Street to Kilburn Street:
Main Street at Pine Street Intersection:
Crews will be installing concrete sidewalks at the corners of Main Street at Pine Street. Crews will work at one corner at a time to maintain pedestrian connections. Crews anticipate starting at the northeast corner before moving to the southeast corner of the intersection. This work will be completed primarily outside of the roadway but may require lane restrictions to accommodate equipment and materials. The intersection will remain open to traffic.
Pine Street – Main Street to Maple Street:
On Wednesday, July 16, crews will be installing the remaining sidewalk along the east side of Pine Street between King Street and Maple Street. Sidewalk work is weather-dependent. This work will require temporary driveway closures while crews form and pour the concrete and allow the concrete to cure long enough to be driven over. Impacted properties will be notified directly in advance. These closures are expected to begin on Wednesday, July 16, at 7 AM and continue through Monday, July 21, at 7 PM due to curb work described below. Pedestrians will be detoured to the west of the roadway. On-street parking restrictions will be in effect during active work hours. Please pay attention to no parking signs throughout the project limits.
On Thursday, July 17, and Friday, July 18, crews will be installing curbs along both sides of Pine Street between Main Street and Maple Street. Curb work is weather-dependent. This work will require the full closure of the King Street and Pine Street intersection. Pine Street between Main Street and Maple Street will be restricted to local traffic only. Pine Street between Main Street and King Street will be accessible from Main Street to the north and Pine Street between King Street and Maple Street will be accessible from Maple Street to the south. Curb work is weather-dependent. This work will require temporary driveway closures while crews install the curb, the concrete the curb is set in cures, and the area can be backfilled. These closures are expected to begin on Thursday, July 17, at 7 AM and continue through Monday, July 21, at 7 PM. Impacted properties will be notified directly in advance. On-street parking restrictions will be in effect during active work hours. Please pay attention to no parking signs throughout the project limits.
Important information regarding parking accommodations for impact properties below!
King Street at Pine Street Intersection:
Potential for independent utility companies to be onsite, relocating aerial utilities at the intersection of King Street and Pine Street. This work will be completed under lane closures with alternating one-way traffic and parking restrictions. The intersection will be completed closed to traffic on Thursday and Friday during active construction hours to accommodate curb installation. King Street will be restricted to local access only and will be accessible from S. Champlain Street to the west and St. Paul Street to the east.
Maple Street at Pine Street Intersection:
Potential for independent utility companies to be onsite, relocating aerial utilities at the intersection of Maple Street and Pine Street. This work will be completed under lane closures with alternating one-way traffic and parking restrictions.
|