Pine Street (north) Kilburn Street to Main Street:
Starting Monday, April 14, and continuing through Wednesday, April 16, crews will install temporary construction signage throughout the project limits including along Pine Street and intersecting side streets between Kilburn Street and Main Street. Two-way traffic will be maintained, temporary traffic shifts and/or shoulder/parking lane closures may be required
Pine Street (north) King Street to Main Street:
Starting Thursday, April 17, and continuing through the end of the month, crews will work at the intersection of King Street and Pine Street and on the segment of Pine Street between King Street and Main Street.
Work at the intersection of King Street at Pine Street will include the removal of curb, sidewalks, and roadway surface to allow for the installation of electrical utility duct bank, traffic signal sleeves and conduit, traffic signal bases, and gravel for road base. The intersection of King Street at Pine Street will be closed to all traffic weekdays (Monday – Friday) during working hours (7AM – 7PM). The intersection will be reopened each night.
Work along Pine Street between King Street and Main Street will include the removal of the roadway surface, sidewalks, and curb. Pine Street between King Street and Main Street will have instances of lane closures with alternating one-way traffic and shoulder/parking lane closures. Pine Street between Maple Street and Main Street will be closed to thru traffic. Businesses will remain open! Local traffic will be able to access businesses and residents along Pine Street north of King Street via Main Street. Thru traffic traveling northbound along Pine Street will be detoured at Maple Street for passenger vehicles and Kilburn Street for trucks. Thru traffic traveling southbound along Pine Street will be detoured at Main Street to St Paul Street to Maple Street for passenger vehicles and Kilburn Street for trucks.
Off the Roadway along the Future Champlain Parkway Alignment:
Work continues along the future Champlain Parkway alignment between Home Avenue and I-189. Topsoiling, seeding, and matting installation will continue along the future Parkway alignment. Crews will continue placing fill material and fine grading the Parkway, and setting light poles and other fixtures on the previously installed bases along the Parkway segment. Crews anticipate completing duct bank installation between Queen City Park Road and the Pine Street cul-de-sac this week and anticipate prepping the area to install granite curb along the cul-de-sac at a later date. These activities will take place off the roadway with limited impact to traffic.
Pine Street at Howard Street:
In the coming weeks, S.D. Ireland will return to the site to complete the installation of the bus shelters just south of the intersection of Pine Street at Howard Street. This work is part of the initial contract which was postponed due to manufacturing delays. These activities will be completed outside of the roadway with minimal impact on traffic. Supplemental information regarding this work will follow.
|