Pine Street
Work continues on Pine Street between Kilburn Street and Lakeside Avenue. Early next week, crew will complete the remaining curb preparation work along the west side of Pine Street, south of Lakeside Avenue near Cumberland Farms, before starting along the east side at the southern construction limit (near Play Dog Play) and working north. Another crew will continue prepping for the installation of curb beginning just south of Kilburn Street and working south. Curb crews will be onsite mid-week install curb along the east side of Pine Street starting at Kilburn Street and progressing south. The rehabilitation and installation of stormwater and drainage infrastructure will continue along both sides of Pine Street throughout the week.
This work will require sections of Pine Street between Kilburn Street and Lakeside Avenue to be under lane shifts or single-lane closures with alternating one-way traffic. There is the potential for the temporary loss of segments of on-street parking to facilitate lane shifts. Two lanes of traffic will be maintained along Pine Street each day between 6:30 a.m. – 9:30 a.m. and 2:30 p.m. - 6:30 p.m. Construction activities along the east and west sides of Pine Street will be staged to provide an appropriate distance between work zones to allow for the maintenance of traffic along the entire length of Pine Street. The bike lanes along Pine Street between Kilburn Street and Lakeside Avenue are closed.
There is the potential for short closures of select side streets at their intersection with Pine Street between Kilburn and Locust Streets to facilitate stormwater infrastructure and drainage work. Each side street closure may take a few days. Side streets will be reopened each evening between the hours of 7:00 p.m. and 7:00 a.m. A detour route will be signed for each closure. Supplemental notices will follow.
Curb installation will require driveways to be reduced to a single lane. Impacted property owners will be notified separately.
|