CONSTRUCTION ACTIVITIES, DURATION, AND TRAFFIC IMPACTS:
Please note, all work will be restricted to the hours of 7:00 a.m. and 7:00 p.m. Flaggers will be present to assist motorists through the work zone. All roadway and lane closures will reopen during the evening hours and on weekends. Access to residential and business driveways will be maintained throughout the work unless alerted otherwise. Businesses will remain open!
Utility work will continue throughout the project along Flynn Avenue, Briggs Street, Lyman Avenue, Ferguson Avenue, Morse Place, Batchelder Street, and Home Avenue. Work will include the installation of new sewer lines, water lines, stormwater infrastructure, duct bank, and conduit.
Throughout next week, crews will complete any remaining water line work and duct bank work along Flynn Avenue between Foster and Briggs Streets. Once the remaining utility work is completed east of the railroad tracks, crews will begin fine-grading Flynn Avenue between Foster Street and just west of Briggs Street in preparation for the installation of pavement. This work will be completed during the daylight hours with alternating one-way traffic.
Crews completed sewer line and sewer service work between Flynn Avenue and Home Avenue and began water work along Briggs Street working south towards Home Avenue. Next week, crews will complete the remaining water line work along Briggs Street before moving onto the side streets including Ferguson Avenue, Lyman Avenue, Morse Place, and Batchelder Street. There is the potential for water service work to begin along Briggs Street and working south to begin late next week. Water service work will require a minor interruption in water service. Impacted property and business owners will be contacted directly by Burlington Water Resources or a member of the project team.
Batchelder Street will remain closed to through traffic. Residential access will be maintained. Through traffic between Home Avenue and Morse Place will be maintained via a temporary roadway constructed just west of Batchelder Street. Morse Place is now reopened to through traffic. Lyman Avenue will reopen at its intersection with Briggs Street by the end of the day Friday, November 11.
Crews will be setting the Englesby Brook box culvert. This work will be completed off the roadway.
Sears Lane will continue to be closed to thru traffic west of Kaigle’s Service Center. Emergency vehicle access will remain. The pedestrian crossing between Sears Lane and Harrison Avenue will remain open. Vehicle access to the HULA Lakeside Offsite Parking Lot (HULA parking lot) will now be from Lakeside Avenue only.
|