CONSTRUCTION ACTIVITIES:
Crews will continue work on utilities next week with a focus on switching over water services and the installation of electrical conduit, stormwater infrastructure, and duct bank.
Water service work is anticipated on Tuesday, December 27, on Ferguson Avenue. This work will require a water service disruption. The water service disruption is anticipated to last for approximately 4 hours and impact businesses and residents along portions of Ferguson Avenue. The water service disruption is tentatively scheduled for Tuesday, December 27, from 9:00 a.m. and 1:00 p.m. Impacted businesses and residents will be notified 48 hours in advance by Burlington Water Resources.
Crews will continue installing stormwater infrastructure between Flynn and Home Avenues along Briggs Street working south starting near Ferguson Avenue. This work will include installing the connections from the mainline on Briggs Street to the side streets such as Ferguson and Lyman Avenues. In addition, crews will be conducting preparatory work for the installation of the new stormwater treatment system to be located in the back parking lot of the Flynn Avenue Co-op located at 288 Flynn Avenue. Next week, crews will be on-site with DigSafe next week to map out underground utilities and the future location of the new sediment-capturing device. After New Years, crews will begin installing the new stormwater treatment system. This work will take a month to complete. Supplemental information will be issued to the residents of the Flynn Avenue Co-op.
Work will continue off the roadway in the area between Sears Lane and Flynn Avenue. Crews will continue working on the stormwater detention pond and installing the drainage and subbase on the area near the box culvert. Later in the week, there is the potential for work installing duct banks along Home Avenue.
Next week, crews will be installing electrical conduit along Ferguson and Lyman Avenues. This work will require service connections to residences over the upcoming weeks. A member of the Champlain Parkway project team has reached out to property owners in advance to schedule service connections.
Independent utility companies will be onsite over the next several weeks relocating existing utilities. Next week, Consolidated Communications will be onsite installing a new utility pole on Home Avenue and Lyman Avenue. BED will relocate a pole on Flynn Avenue.
|