Construction Update

Champlain Parkway Project

DATE: Friday, August 12, 2022

SPECIAL ANNOUNCEMENTS:

Sears Lane will continue to be closed to through traffic west of Kaigle’s Service Center. Emergency vehicle access will remain. The pedestrian crossing between Sears Lane and Harrison Avenue will remain open. Vehicle access to the HULA Lakeside Offsite Parking Lot (HULA parking lot) will now be from Lakeside Avenue only.  

CONSTRUCTION ACTIVITIES, DURATION, AND TRAFFIC IMPACTS:

Crews will be on-site Monday, August 15, through Friday, August 19, between the hours of 7:00 a.m. and 7:00 p.m. All work will be completed off the roadway within the project Right of Way.


Throughout the week, crews will continue stormwater work between Lakeside Avenue and Sears Lane. Crews will continue excavating and shaping the sand filter just west of the Champlain College Miller Building on Lakeside Avenue. Crews completed excavating and will begin installing the underdrain along the west side of 40 Sears Lane between Sears Lane and the parking area.


Crews have excavated the area from the stormwater detention pond working south towards Flynn Avenue and will begin installing the associated stormwater infrastructure. Next week, cranes will be mobilized onsite to assist in the placement and installation of stormwater structures. Ground improvements will continue throughout the area creating noticeable vibrations.


Crews will begin excavating the roadway alignment for the Champlain Parkway east of Briggs Street within the City’s Right of Way starting at Flynn Avenue and working towards the south. No roadway alignment work will be completed at the intersecting side streets (Ferguson Avenue, Lyman Avenue, and Morse Place) next week.  

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract includes the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street. 

PROJECTED COMPLETION: Initial Contract 2024

                                                    Final Contract 2027

Project Website

CONTACT US:

For more information about the project please visit the project website champlainparkway.com or contact the project team via the project hotline, 802-496-8956 or by email: info@champlainparkway.com.

Facebook  Twitter