|
Pine Street – East and West
On Monday, August 26, crews will adjust structures along Pine Street in preparation for paving the final wearing course of asphalt later in the week. On Wednesday, August 28, crews will mill (remove the surface layer of pavement) at the northern and southern project limits of Pine Street in preparation for final paving operations to tie the new pavement into the existing. This work will require lane closures with alternating one-way traffic. There is the potential for paving the remaining portion of the shared use path between Lakeside Avenue and Burlington City Arts next week. This work will require driveways to be reduced to half width while the aprons are paved and a short 10–15-minute driveway closure to facilitate the paving of the shared use path.
On Thursday, August 29 and Friday, August 30, crews will pave the final wearing course of asphalt on Pine Street within the project limits starting just north of Kilburn Street and progressing south near Play Dog Play. Final paving operations may take place overnight and require Pine Street to be restricted to one lane with northbound-only traffic. A supplemental notice will follow. Paving operations are weather-dependent.
In addition, crews will continue topsoiling, backfilling hardscape surfaces, and sign restoration along either side of Pine Street throughout the week.
Pine Street at Locust Street
Today, Friday, August 23, crews will be milling at the intersection of Locust Street and Pine Street in advance of paving at this location on Monday, August 26. Paving operations are weather-dependent. This work will require width reductions along Locust Street and a potential lane reduction on Pine Street with alternating one-way traffic controlled by flaggers.
Pine Street at Howard Street, Marble Avenue, and Kilburn Street
Crews will continue prepping and installing brick pavers at the raised intersections of Pine Street at Howard Street, Marble Avenue, and Kilburn Street. The raised intersections include the area bound by the concrete transitions (as shown in the graphic below). Early next week, crews will complete brick paver installation at the intersection of Pine Street at Howard Street. Once completed, crews will begin working at the intersection of Pine Street at Kilburn Street. This work will require a single-lane closure with alternating one-way traffic on Pine Street and temporary closures of the side roads at their intersection with Pine Street. Lane reductions and side road closures will be in effect 24 hours a day, 7 days a week while this work is completed. Brick paver installation will be completed one intersection at a time with each intersection taking approximately two weeks to complete.
|