Pine Street (north) Main Street to Kilburn Street:
Pine Street will be open to traffic between Main Street and Kilburn Street. Instances of lane closures with traffic maintained will take place at the intersections of King Street and Pine Street and Maple Street and Pine Street for independent utility work. No vehicular detours, including the truck detour via Kilburn Street and St. Paul Street, will be in effect.
Main Street at Pine Street Intersection:
Crews will begin forming and pouring concrete sidewalk at the intersection of Main Street at Pine Street continuing over the next few weeks. This work will be completed primarily outside of the roadway, but may require parking or lane restrictions to accommodate equipment and materials. The intersection will remain open to traffic. Pedestrians will be detoured around to avoid sections of sidewalk as they are constructed.
Pine Street – Main Street to King Street:
Crews will install concrete sidewalk along the east side of Pine Street just north of King Street. This work will take place predominantly off the roadway. Sidewalk work is weather-dependent. This work will require temporary driveway closures lasting 48 hours while crews form and pour the concrete and allow the concrete to cure long enough for it to be plated. Impacted properties will be notified directly in advance. Pedestrians will be detoured to the open travel path on either side of the roadway.
King Street at Pine Street Intersection:
Early next week, independent utility companies will be working to relocate aerial utilities at the intersection of King Street and Pine Street. This work will be completed under lane closures with alternating one-way traffic and parking restrictions.
Maple Street at Pine Street Intersection:
Next week, independent utility companies will be working to relocate aerial utilities at the intersection of Maple Street and Pine Street. This work will be completed under lane closures with alternating one-way traffic and parking restrictions.
|