Champlain Parkway Project

DATE: Friday, June 27, 2025

TRAVEL NOTICE:

The segment of the Champlain Parkway between Interstate 189 and Home Avenue is not completed and is not open for public access. Active construction continues along this segment which includes the movement and transport of construction vehicles, equipment, and materials. All other access (vehicular, pedestrian, or bicycle) is strictly prohibited.

CHAMPLAIN PARKWAY & MAIN STREET GREAT STREETS HIGHLIGHTS:

The Burlington Department of Public Works maintains a construction map containing traffic impacts, including traffic restrictions, roadway closures, and more, for all major construction projects in the Downtown District and the South End. Plan your travel with the most up-to-date information by using the map here.


Traffic impact highlights for the Champlain Parkway Project for Monday, June 30, through Thursday, July 3, are listed below:

  • Main Street at Pine Street Intersection: Open to vehicular traffic. Potential lane reductions to accommodate sidewalk work. Pedestrian detours throughout the week.
  • Pine Street – Main Street to King Street: Sidewalk work will require on-street parking restrictions.
  • King Street at Pine Street Intersection: Early next week, intermittent lane closures with alternating one-way traffic to facilitate independent utility work.
  • Pine Street – King Street to Maple Street: Fully open to traffic.
  • Maple Street at Pine Street Intersection: Intermittent lane closures with alternating one-way traffic to facilitate independent utility work.
  • Pine Street – Maple Street to Kilburn Street: Fully open to traffic.
  • Future Champlain Parkway – I-189 to Home Avenue: Fully closed, all traffic strictly prohibited.  


For more detailed information on construction activities and traffic impacts related to the Champlain Parkway Project, read the Construction Update section below.


Traffic impact highlights for the Main Street – Great Streets Project for Monday, June 30, through Thursday, July 3, are listed below:

  • Main/S. Winooski: Fully closed to vehicles.
  • Main: S. Winooski to Church: Fully closed to vehicles.
  • Main/Church: Closed to vehicle traffic during the day. Open to vehicle traffic nights and weekends.
  • Main: St. Paul to Pine: Open to two-way traffic nights and weekends.
  • While business access remains, some pedestrian detours may be in place along sidewalks on Main St. between Pine and St. Paul
  • Main/St. Paul: Open to vehicle traffic. Will close for up to three days the week of 6/30 for paving.
  • Main/Pine: Open to vehicular traffic. Flagged traffic possible Mon-Wed next week.

For additional information on the Great Streets – Main Street Project or to view the latest construction updates and traffic impacts, visit the project website by using the link here.

Construction Update

DURATION:

Unless otherwise noted, work will be restricted to the hours of 7 a.m. and 7 p.m., Monday through Friday.


In observance of Independence Day (Fourth of July), crews will be offsite starting Thursday, July 3, at noon, through Monday, July 7, at 7 a.m. 

CONSTRUCTION ACTIVITIES & TRAFFIC IMPACTS:

Pine Street (north) Main Street to Kilburn Street:

Pine Street will be open to traffic between Main Street and Kilburn Street. Instances of lane closures with traffic maintained will take place at the intersections of King Street and Pine Street and Maple Street and Pine Street for independent utility work. No vehicular detours, including the truck detour via Kilburn Street and St. Paul Street, will be in effect. 


Main Street at Pine Street Intersection:

Crews will begin forming and pouring concrete sidewalk at the intersection of Main Street at Pine Street continuing over the next few weeks. This work will be completed primarily outside of the roadway, but may require parking or lane restrictions to accommodate equipment and materials. The intersection will remain open to traffic. Pedestrians will be detoured around to avoid sections of sidewalk as they are constructed.   


Pine Street – Main Street to King Street:

Crews will install concrete sidewalk along the east side of Pine Street just north of King Street. This work will take place predominantly off the roadway. Sidewalk work is weather-dependent. This work will require temporary driveway closures lasting 48 hours while crews form and pour the concrete and allow the concrete to cure long enough for it to be plated. Impacted properties will be notified directly in advance. Pedestrians will be detoured to the open travel path on either side of the roadway.


King Street at Pine Street Intersection:

Early next week, independent utility companies will be working to relocate aerial utilities at the intersection of King Street and Pine Street. This work will be completed under lane closures with alternating one-way traffic and parking restrictions.


Maple Street at Pine Street Intersection:

Next week, independent utility companies will be working to relocate aerial utilities at the intersection of Maple Street and Pine Street. This work will be completed under lane closures with alternating one-way traffic and parking restrictions.   

Off the Roadway along the Future Champlain Parkway Alignment:

Work continues along the future Champlain Parkway alignment between Home Avenue and I-189. Crews will continue paving the Champlain Parkway alignment. These activities will take place off the roadway with limited impact on traffic. Please note, there will be increased construction vehicle traffic at the Parkway and Shelburne Street (Route 7) and Home Avenue. Motorists are reminded that this segment of the Champlain Parkway is NOT open to traffic of any kind.

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract, conditionally accepted in December 2024, included the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street.



The final contract, which broke ground in January 2025, includes the construction of the Champlain Parkway from existing I-189 near its intersection with U.S. Route 7 to Home Avenue and the section of Pine Street between Kilburn Street and Main Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2026