CONSTRUCTION ACTIVITIES:
Crews will continue excavating along Lakeside Avenue between Pine Street and the westerly driveway of 128 Lakeside Avenue (the Innovation Center) to facilitate the installation of underground utilities (waterline, electrical vaults, conduit, ductbank, and stormwater infrastructure) and the reconstruction of the roadway. Crews will also be installing traffic signal equipment at the intersection of Lakeside Avenue and the Parkway alignment. This work will be completed under the full closure of Lakeside Avenue within the project limits.
Crews will continue reconstructing Flynn Avenue between Foster Street and the railroad crossing. Crews will fine-grade and pave the reconstructed segment of Flynn Avenue under single-lane closures. Motorists should expect a gravel surface along portions of Flynn Avenue throughout the week. This may require minor impacts to driveway along Flynn Avenue access to businesses and residents will be maintained.
Traffic signal equipment will be installed on Sears Lane at its intersection with the Champlain Parkway. This work will require minimal impacts to traffic.
Crews will complete additional work outside of the roadway throughout the project area. Crews will continue installing conduit and top soiling and seeding along the Champlain Parkway alignment between Home Avenue and Lakeside Avenue.
|