Construction Update

Champlain Parkway Project

DATE: Friday, October 7, 2022

SPECIAL ANNOUNCEMENTS:

Blasting activities have been postponed! Drilling is scheduled to begin Monday, October 10 and blasting activities are scheduled to begin Tuesday, October 11.


Blasting activities along the east side of Briggs Street between Flynn Avenue and Ferguson Avenue are scheduled to begin Tuesday, October 11. Blasting operations will require intermittent traffic stoppages in the area prior to each blasting event. For additional information on the blasting procedure and impacts, click here.

CONSTRUCTION ACTIVITIES, DURATION, AND TRAFFIC IMPACTS:

Utility work will continue throughout the project along Flynn Avenue, Briggs Street, and Morse Place. Work will include the installation of new sewer lines, water lines, stormwater infrastructure, duct bank, and conduit.


Crews will continue installing sewer line along Flynn Avenue between Foster Street and the railroad tracks working west. Once sewer line is installed, crews will begin installing water line. This work will be completed under a single lane closure with alternating east-west traffic. Work will be restricted to the hours of 7:00 a.m. to 7:00 p.m. Flaggers will be present to assist motorists through the work zone.


Flynn Avenue will reopen to two-way traffic during the evening hours between 7:00 p.m. and 7:00 a.m and on weekends. Access to Briggs Street, residential and business driveways will be maintained throughout the work. Businesses will remain open! The remaining utility work will be completed over the next several weeks. For additional information and graphics, click here.


Crews will continue installing sewer line between Lyman Avenue and Home Avenue. Next week, work will focus on the area near Morse Place and Batchelder Street. This work will be completed under single lane closures with alternating traffic. Work will be restricted to the hours of 7:00 a.m. to 7:00 p.m. Flaggers will be present to assist motorists through the work zone. The roadways will reopen to two-way traffic during the evening hours between 7:00 p.m. and 7:00 a.m. Access to residential and business driveways will be maintained throughout the work. Late next week, there is the potential for a single day closure of Morse Place to through traffic at its intersection with Batchelder Street. A traffic alert will be issued next week to notify stakeholders of this closure.


Stormwater infrastructure will be installed along the Champlain Parkway roadway alignment between Sears Lane and Flynn Avenue. This work will be completed off the roadway. Crews will begin prepping the roadway alignment between Sears Lane and Lakeside Avenue for the installation of curb.


Crews will be completing clean up work along Sears Lane. Sears Lane will continue to be closed to thru traffic west of Kaigle’s Service Center. Emergency vehicle access will remain. The pedestrian crossing between Sears Lane and Harrison Avenue will remain open. Vehicle access to the HULA Lakeside Offsite Parking Lot (HULA parking lot) will now be from Lakeside Avenue only. 


Crews will continue working on the stormwater detention pond near Englesby Brook and the sandfilter near Lakeside Avenue adjacent to the Champlain College Miller Center building. This work will be completed off the roadway.

PROJECT LOOK AHEAD (OCTOBER 17-21): 


These activities are anticipated and subject to change as construction conditions dictate.


  • Utility work will continue throughout the project:
  • Flynn Avenue will remain under lane reduction
  • Briggs Street will remain under lane reduction
  • Morse Place at its intersection with Batchelder Street may require a single-day closure (residential driveways and Batchelder Street will remain open)
  • Stormwater work will continue off the roadway between Sears Lane and Flynn Avenue
  • Blasting activities will continue along Briggs Street
  • Work will continue on the stormwater detention pond and sandfilter

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract includes the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2027

Project Website

CONTACT US:

For more information about the project please visit the project website champlainparkway.com or contact the project team via the project hotline, 802-496-8956 or by email: info@champlainparkway.com.