Construction Update

Champlain Parkway Project

DATE: Friday, September 9, 2022

SPECIAL ANNOUNCEMENTS:

Early morning, Monday, September 12, there is a planned temporary water service disruption along Sears Lane. Water service is anticipated to be restored by the early afternoon. Impacted property owners have been notified by Burlington Water Resources (click here to read the full notice).

CONSTRUCTION ACTIVITIES, DURATION, AND TRAFFIC IMPACTS:

Sears Lane will continue to be closed to thru traffic west of Kaigle’s Service Center. Emergency vehicle access will remain. The pedestrian crossing between Sears Lane and Harrison Avenue will remain open. Vehicle access to the HULA Lakeside Offsite Parking Lot (HULA parking lot) will now be from Lakeside Avenue only. 


Utility work continues on Sears Lane between Kaigle’s Service Center and 40 Sears Lane. Crews will continue working on the water line, duct bank, and stormwater infrastructure. In addition, crews will begin reconstructing Sears Lane.


Monday, September 12, through Friday, September 16, Sears Lane will be reduced to one lane with alternating one-way traffic between Pine Street and Kaigle’s Service Center between the hours of 7:00 a.m. and 7:00 p.m. Sears Lane will be reopened to two lanes with two-way traffic between 7:00 p.m. and 7:00 a.m. Flaggers will be present to assist travelers through the work zone. Driveway access will be maintained.


Crews will continue working on the outflow structures from the stormwater detention pond to Englesby Brook and prepping for the installation of the box culvert. Crews will be constructing the embankment on either side of the brook. Crews will continue to excavate and construct the new road between Sears Lane and the box culvert. 

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract includes the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2027

Project Website

CONTACT US:

For more information about the project please visit the project website champlainparkway.com or contact the project team via the project hotline, 802-496-8956 or by email: [email protected].

Facebook  Twitter