Champlain Parkway Project

DATE: Friday, April 4, 2025

PROJECT UPDATE:

In the coming weeks, work along Pine Street between Kilburn Street and Main Street related to the Champlain Parkway Project will begin with construction signage installation starting the week of April 14. Construction activities will consist of the rehabilitation of the roadway, including new curbing, pavement, line striping, roadway signage, and stormwater improvements. New traffic signals will be installed at the Maple Street, King Street, and Main Street intersections. Improvements to pedestrian accommodations will include protected pedestrian crossing phases at the new signals, a mid-block crossing between Kilburn Street and Maple Street, new sidewalks along both sides of the roadway, and new brick paver crosswalks at Maple Street and King Street.


Work continues along Main Street between Pine Street and South Winooski Avenue as part of the Great Streets Main Street Project. Due to the proximity and overlap of the two construction projects, the two project teams are coordinating construction impacts and detour routes. 



The Burlington Department of Public Works maintains a construction map containing traffic impacts including traffic restrictions, roadway closures, and more for all major construction projects in the Downtown District and the South End. Plan your travel with the most up-to-date information by using the map here.


For additional information on the Great Streets – Main Street Project or to view the latest construction updates and traffic impacts, visit the project website by using the link here.

Construction Update

DURATION:

Unless otherwise noted, work will be restricted to the hours of 7 a.m. and 7 p.m., Monday through Friday. 

CONSTRUCTION ACTIVITIES & TRAFFIC IMPACTS:

Off the Roadway along the Future Champlain Parkway Alignment:

Work continues along the future Champlain Parkway alignment between Home Avenue and Shelburne Street (Route 7). Crews will continue placing fill material and fine grading the Parkway starting at Home Avenue and continuing south and begin setting light poles on the previously installed bases along the Parkway segment. Duct bank will continue to be installed along the Champlain Parkway focusing on the section between Queen City Park Road and the Pine Street cul-de-sac. General clean-up and erosion prevention work continue along the alignment. These activities will take place off the roadway with limited impact to traffic.



Pine Street at Howard Street:

In a few weeks, S.D. Ireland will return to the site to complete the installation of the bus shelters just south of the intersection of Pine Street at Howard Street. This work is part of the initial contract which was postponed due to manufacturing delays. These activities will be completed outside of the roadway with minimal impact on traffic. In advance of this work, DigSafe will be onsite marking existing utilities. Supplemental information regarding this work will follow.

PUBLIC SAFETY ANNOUNCEMENT:

Pine Street is permanently closed between Queen City Park Road and South Crest Drive and is an active work zone! Access for vehicles, pedestrians, and bicycles is restricted to local traffic only; through traffic of all kinds is strictly prohibited.


The section of the shared-use path beginning just south of the Buffalo Wild Wings on Shelburne Street (U.S. 7) and continuing to just north of the new cul-de-sac Pine Street (near the Howard Center) is open and available for use by cyclists and pedestrians. Please note, the path is not paved on the U.S. 7 end. Please use caution and watch out for varying surface conditions.


The unused section of the previously constructed Southern Connector between Shelburne Street (Route 7) and Home Avenue is an active work zone! For your safety, access for vehicles, pedestrians, and cyclists is strictly prohibited.


Crews will access the work zone from the western end of Home Avenue at the Champlain Parkway as well as from Shelburne Street near Buffalo Wild Wings via the ramp to the future Champlain Parkway. Travelers are encouraged to drive slowly and watch for construction vehicles and equipment entering and exiting the work zone. Additionally, travel along the ramp and unused section of the Southern Connector is restricted to construction vehicles and equipment only.

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract, conditionally accepted in December 2024, included the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street.



The final contract, which broke ground in January 2025, includes the construction of the Champlain Parkway from existing I-189 near its intersection with U.S. Route 7 to Home Avenue and the section of Pine Street between Kilburn Street and Main Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2026