CONSTRUCTION ACTIVITIES:
Crews will continue work on utilities with a focus on completing the waterline work and the installation of stormwater infrastructure, underdrain, and electrical and telecommunication utilities. Some of this work will be completed under road and lane closures as described above.
Crews will work to complete the remaining waterline work on Ferguson Avenue, Lyman Avenue, and Morse Place.
Crews will continue installing stormwater infrastructure between Flynn and Home Avenues. This work will include installing the mainline along Briggs Street and Batchelder Street starting near Lyman Avenue and the connections to the side streets such as Ferguson Avenue, Lyman Avenue, and Morse Place. The connections to the side streets are anticipated to being later in the week and continue into the following. The work will require traffic shifts along Briggs Street and closures of Ferguson Avenue, Lyman Avenue, and Morse Place at their intersection with Briggs Street.
Crews will be installing underdrain along the parkways alignment beginning just north of Flynn Avenue working south towards Home Avenue. This work will take place off the roadway. This work will require closures of Ferguson Avenue, Lyman Avenue, and Morse Place at their intersection with the parkway alignment to complete those segments. These closures are anticipated to begin the following week.
Crews continue working on electrical and telecommunications work for residences on Briggs Street, Ferguson, Lyman, and Home Avenues. This work will require service connections to residences over the upcoming weeks. All property owners have been notified.
Independent utility companies will be onsite over the next several weeks relocating existing utilities. There is the potential for utility service disruptions as part of this work. Impacted businesses and residents will be notified in advance by the independent utility companies.
|