Champlain Parkway Project

DATE: Monday, October 6, 2025

Traffic Alert

MAPLE STREET (WEST) CLOSED UNTIL TOMORROW MORNING, MAPLE STREET (EAST) ON TRACK TO REOPEN TOMORROW EVENING


Crews continue to work to complete the brick paver crosswalks at the intersection of Maple Street at Pine Street. The installation of the crosswalk across the west leg of Maple Street has been completed. The polymeric sand, used to lock the bricks in place and prevent plant growth between the bricks, is curing overnight. The reopening of the west leg of Maple Street has been delayed until tomorrow morning, Tuesday, October 7. Tomorrow, crews will complete the installation of the crosswalk across the east leg of Maple Street, including the installation of brick and polymer sand and paving the approaches. The reopening of the east leg of Maple Street is on track for the end of the day tomorrow.


During these closures, Maple Street (west) will be accessible via S. Champlain Street and Maple Street (east) will be accessible via St. Paul Street. Throughout the week, traffic will not be able to continue south along Pine Street from the Maple Street intersection. 

For additional information regarding construction activities for the week of Monday, October 6, through Friday, October 10, read the full Construction Update by clicking here.


To receive updates on the project, construction activities and impacts, and major milestones straight to your inbox, fill out the online form here, or by checking the project website, champlainparkway.com.

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract, conditionally accepted in December 2024, included the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street.



The final contract, which broke ground in January 2025, includes the construction of the Champlain Parkway from existing I-189 near its intersection with U.S. Route 7 to Home Avenue and the section of Pine Street between Kilburn Street and Main Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2026

CONTACT US:

For more information about the project, please visit the project website champlainparkway.com, or contact the project team via the project hotline, 802-496-8956, or by email: info@champlainparkway.com.