Champlain Parkway Project

DATE: Wednesday, October 15, 2025

Traffic Alert

Final Paving along Pine Street between Main Street and Kilburn Street Continues; Sequencing and Traffic Pattern Changes


Today, Wednesday, October 15, crews are paving the sections of Pine Street between Maple Street and Kilburn Street and between King Street and Maple Street. This work requires these segments to be reduced to a single lane with alternating one-way traffic and to be restricted to local traffic only. Access to businesses and residents will be maintained; however, paving will require traffic holds at residential and business driveways of approximately 30 minutes while the asphalt cools.

 

Tomorrow, Thursday, October 16, crews will pave the intersections of Maple Street at Pine Street and King Street at Pine Street. This work will require the full closure of the intersection of Maple Street at Pine Street in the morning and the King Street at Pine Street in the afternoon. The intersections will not be closed simultaneously. During the Maple and Pine intersection closure, the segment of Pine Street between Maple Street and Kilburn Street will be restricted to local traffic only and remain accessible from the south via Kilburn Street. During the King and Pine intersection closure, the segment of Pine Street between King Street and Maple Street be restricted to local traffic only and will remain accessible from the south via Maple Street.

 

Paving along Pine Street between King Street and Main Street and the intersection of Main Street at Pine Street could take place as early as Friday, October 17. There is the potential for paving of this section to be rescheduled to early next week. A supplemental notice will be issued tomorrow, Thursday, October 16. This work will require the segment to be reduced to a single lane with alternating one-way traffic and to be restricted to local traffic only. Access to businesses and residents will be maintained; however, paving will require traffic holds at residential and business driveways of approximately 30 minutes while the asphalt cools. This work will require the full closure of the intersection of Main Street at Pine Street. During the intersection closure, the segment of Pine Street between Main Street and King Street will be restricted to local traffic only and will remain accessible from the south via King Street.

 

Travelers should continue to expect delays and seek alternative routes when possible. 

For additional information regarding construction activities for the week of Monday, October 13, through Friday, October 17, read the full Construction Update by clicking here.


To receive updates on the project, construction activities and impacts, and major milestones straight to your inbox, fill out the online form here, or by checking the project website, champlainparkway.com.

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract, conditionally accepted in December 2024, included the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street.



The final contract, which broke ground in January 2025, includes the construction of the Champlain Parkway from existing I-189 near its intersection with U.S. Route 7 to Home Avenue and the section of Pine Street between Kilburn Street and Main Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2026