Champlain Parkway Project

DATE: Tuesday, November 4, 2025

Traffic Alert

Line Striping along Pine Street between Main Street and Kilburn Street Anticipated to Begin Tomorrow, Wednesday, November 5, Weather Permitting


TOMORROW, Wednesday, November 5, L&D is anticipated to be onsite to begin installing line striping and pavement markings along Pine Street between Main Street and Kilburn Street. This work is weather-dependent. Line striping and pavement marking activities will continue throughout the rest of this week and potentially into the following.

 

Pine Street will be restricted to local traffic only; access to businesses and residents will be maintained. Traffic holds and lane closures with alternating one-way traffic or traffic shifts will be in effect. Drivers, especially traffic entering and existing driveways along Pine Street, may be held for up to 30 minutes while the epoxy cures. Cure times are dependent on temperature. Motorists are advised to plan extra travel time.

 

This work will cause major impacts to traffic; motorists should expect delays and seek alternate routes whenever possible. A detour route will be signed utilizing Kilburn Street, St. Paul Street, and College Street.

For information regarding other construction activities and impacts taking place the week of November 3 through the 7, read the full Construction Update by clicking here.


To receive updates on the project, construction activities and impacts, and major milestones straight to your inbox, fill out the online form here, or by checking the project website, champlainparkway.com.

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract, conditionally accepted in December 2024, included the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street.



The final contract, which broke ground in January 2025, includes the construction of the Champlain Parkway from existing I-189 near its intersection with U.S. Route 7 to Home Avenue and the section of Pine Street between Kilburn Street and Main Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2026