Helicopter Lift: 118 N Clark Street
On Saturday, March 8, from 8am to 12pm, there will be a helicopter lift at 118 N Clark Street. During the lift, the following will be closed to vehicular and pedestrian traffic:
- North Clark Street, between West Randolph Street and West Washington Street
- West Randolph Street & West Washington Street, between North Dearborn Street and North LaSalle Street
Filming: 666 N Orleans
Minim Productions, Inc will be filming scenes for the TV Show titled “FOUR SEASONS” in your neighborhood on:
Tuesday March 11, 2025 – Thursday March 13, 2025
In order to park essential vehicles and equipment, streets in your area will be posted as a NO PARKING/TOW ZONE during the following dates/times:
Tuesday March 11, 2025 (5AM) – Wednesday March 12, 2025 (3PM)
West Side of Orleans St from Huron St to Erie St
South Side of Huron St from Sedgwick St to Franklin St
Wednesday March 12, 2025 (3PM) – Thursday March 13, 2025 (11:55PM)
South Side of Erie St from Orleans St to Sedgwick St
Both Sides of Erie St from Orleans St to Franklin St
West Side of Orleans St from Huron St to Erie St
South Side of Huron St from Hudson St to Franklin St
North Side of Huron St from Orleans St to Franklin St
ALLEY CLOSURE - Thursday March 13, 2025 (9AM – 9PM)
Alley between Huron St and Erie St and Sedgwick St
INTERMITTENT TRAFFIC CONTROL - Thursday March 13, 2025 (7PM – 11PM)
Franklin St from Huron St to Ontario St & Erie St from Orleans St to Wells St
Helicopter Lift: 100 East Bellevue Place
On Saturday, March 22nd there will be a helicopter lift at 100 E Bellevue Pl between 8 am-12pm. During the lift, the following will be closed to vehicular traffic:
- Bellevue Pl from Lake Shore drive to alley east of Rush Street
- Inner Lake Shore Drive between Cedar Street and Oak Street
- Alley between Bellevue Pl and Cedar Street
Casino Caisson Pours: February 24 - April 18
Construction crews will begin to pour roughly 46 caissons for the new casino on Monday, February 24 - pending permit approval. Caisson pours are expected to last until Friday, April 18.
Work hours will continue to be 8am-8pm. However, if an issue arises during a pour, there is the potential that crews will work past 8pm. Once a caisson pour begins, it can't stop until it is finished.
In the event this happens, Bally's is supposed to notify our office so we can inform the community.
676 North Michigan Avenue Façade Project
Redmond Construction was hired to complete a façade project at 676 North Michigan Avenue. Currently, the following closures are in-place:
- Sidewalk on the south side of Huron, from Michigan Avenue to a point 150' west thereof
- Curb lane on the south side of Huron, from Michigan Avenue to a point 150' west there of is being used as a pedestrian walkway
- Partial sidewalk closure the west side of Michigan, from Huron to a point 100' south thereof
This project is expected to be completed by fall 2025.
River North Lighting Project
The Chicago Department of Transportation (CDOT) has completed new light pole installation in the area bounded by Chicago, Ontario, Orleans, and the River. CDOT has begun removal of the old light poles and continues to restore infrastructure trenching.
Pin & Link Project on Randolph and Columbus
CDOT crews are scheduled to perform steel work and bridge expansion joint rehab along Randolph Street, Columbus Drive, and Stetson Avenue. Please see details below:
General Construction Schedule:
7:00 am - 3:30 pm, Monday - Friday; with the occasional extension to 5:30 pm as needed.
Scope of Work and Access Impacts During Construction:
In general, one lane of travel will be open at all times along each roadway, level, and direction. Access along sidewalks will remain open with detours around the work areas.
This project is expected to be completed at the end of June 2025. Asphalt restoration will occur in July 2025.
Casino Demolition Update
The demolition team will begin site concrete crushing operations over the next eight weeks. The operation with run from 8 AM until 5 PM. The crusher will be placed in between the Ontario feeder ramp and the southern edge of the current building.
|