Scan the QR Code to visit the Clayton County Special Purpose Local Option Sales Tax website where you will find the status
and photos of active SPLOST projects.
Clayton County
Special Purpose Local Option Sales Tax (SPLOST)
Project Updates
A new 103,000 sq. ft. three-story Clayton County Administration Building will be located on an
18-acre parcel of land on Old Poston Road in Jonesboro. The facility will be home to several county departments including the Board of Commissioners, Finance, Human Resources, Legal and Communications.
Update: Building designs from Nelson Worldwide architecture firm are due the first week of March. A meeting to discuss the possibility of including public electric vehicle charging stations with county leaders is scheduled for March 1.
Construction Firm:
To Be Determined
Design Firm:
Nelson Worldwide
Project Completion:
August 2025
New welcome signs will be strategically placed at the North, South, East, and West entrances of the county. The welcome signs will showcase the county's new brand logo to welcome and engage our citizens and visitors when entering the County, including the airport area.
Update: The signage is being manufactured and installation estimated to begin in April.

 
Construction Firm:
To Be Determined
Design Firm:
DeNyse
Project Completion:
November 2023
The Small Business Incubator will provide resources to introduce, connect, support, and expand new businesses in Clayton County to bolster the creation of jobs, investment, and economic development.
Update: Four bids were received by the county to design and build the new space. Vendor interviews with Central Services are scheduled for Jan. 26, with recommendations due on Feb. 6.
Construction Firm:
To Be Determined
Design Firm:
To Be Determined
Project Completion:
To Be Determined
The senior center’s interior is receiving a complete renovation to include bathroom upgrades, interior lighting replacement, installing a new washer and dryer and interior wall and ceiling finishes to include wall patching and painting. A new entrance canopy with two new ADA compliant ramps for accessibility will round out the exterior renovations.
Update: The interior flooring, ceiling, and painting projects are now finished. Planning, Design and Construction is assembling a proposal for an exterior canopy.
Construction Firm:
Numerous Contractors
Design Firm:
Gardner Spencer Smith
Completion Date:
To Be Determined
The Fleet Maintenance Expansion Project will revitalize the existing facility to include an upgrade to its electrical system, new HVAC, vehicle lifts, flooring, windows, and doors. In addition, a new oil pump system and air lines are planned as well as painting the interior and exterior of the building.
Update: The interior painting of the first and second floors has been completed. Exterior painting will begin when outside temperatures increase. Plans to replace the flooring are moving forward.
Construction Firm:
Numerous Contractors
Design Firm:
Not Applicable
Completion Date:
To Be Determined
The construction of a free-standing Crisis Stabilization Unit and/or Behavioral Health Crisis Center to treat urgent or emergency psychiatric needs. Care would include stabilization services in a safe, structured manner with continuous 24-hour observation and supervision.
Update: The masterplan for the new facility is complete and project cost estimates are expected to be submitted by Feb. 22.
Construction Firm:
Pyramid Remedial Services
Design Firm:
Jericho Design Group
Completion Date:
To Be Determined
This project consist of constructing an asphalt ADA accessible walking trail from Plantation Parkway crossing over Harbour Town Parkway continuing to Harbour Lake Drive cul-de-sac through 16.32 acres.
Update: Diversified Construction has completed paving on the northern and southern portion of the trails. A task list of items needing correction has been provided to Diversified Construction by Prime Engineering, which includes repaving of several portions of the trail. Planning, Design and Construction is awaiting an updated project timeline from Diversified Construction.
Construction Firm:
Diversified Construction
Design Firm:
Prime Engineering
Completion:
To Be Determined
Renovations of the VIP Complex at International Park integrate outdoor spaces while maintaining a multi-functional facility for arts and entertainment. Other enhancements include additional covered seating, event administrative space, dressing rooms, additional concessions, re-design of restrooms, backstage facilities, and vendor kiosks.
Update: Design and construction plans are in review with Community Development.
Construction Firm:
To Be Determined
Design Firm:
Gardner Spencer Smith
Completion Date:
April 2024
The new Winter Weather Supply and Storage Building will be located behind the Clayton County Jail on Post Way in Jonesboro. The facility will be used to store approximately 14 days of cold weather material such as salt, sand, and gravel. In addition, it will serve as storage for a salt brine maker and brine solution and house snowplows and spreaders.
Update: Clayton County Central Services hosted a project outreach and site visit with potential vendors on Feb. 22. Five contractors attended the Industry Day to gather specific project information.
Construction Firm:
To Be Determined
Design Firm:
To Be Determined
Completion Date:
To Be Determined
Clayton County Tennis Courts
Tennis courts at the International Park Tennis Center, Gerald Matthews Tennis Complex, Independence Park and Flat Shoals Park will be resurfaced with new fencing and landscaping installed. The $1.16 million project is estimated to eight to 10 months to complete. 
Update: Demolition is ongoing by Signature Tennis Courts Inc. Once all asphalt has been removed, ground leveling will begin.
Construction Firm:
Signature Tennis Courts INC.
Design Firm:
N/A
Completion date:
October 2024
Clayton County Fire Station No. 1 Replacement
The new Fire Station No. 1 will be a replacement facility for the existing Fire Station No. 1 in Riverdale.
Update: Updates requested by the Clayton County Water Authority are being added to design documents by POND & Company architects. 
Construction Firm:
To Be Determined
Design Firm:
To Be Determined
Completion date:
To Be Determined
Clayton County Fire Station No. 2 Replacement
The new Fire Station No. 2 will be a replacement facility for the existing Fire Station No. 2 in Rex.
Update: Planning, Design and Construction is awaiting cost estimates for a sewer connection installation. Architectural firm POND & Company is revising designs prior to submittal to Community Development and the Clayton County Water Authority for review.
Construction Firm:
To Be Determined
Design Firm:
To Be Determined
Completion date:
To Be Determined
Please note all dates are subject to change due to numerous variabilities such as shipping delays and weather.
Access the claytonsplost.com website for more information on projects and improvements throughout Clayton County thanks to the 1-cent sales tax.
Clayton County Board of Commissioners
Clayton County Board of Commissioners
112 Smith Street
Jonesboro, GA 30236
Main Office: 770-477-3208
www.claytoncountyga.gov
www.claytonsplost.com

Office of Communications
121 S. McDonough Street
Jonesboro, GA 30236
#Claytonconnected
Get Clayton connected
Go Mobile With Us
Get The Click Clayton Mobile App