In the survey, some asked for more community build updates from the Developer. Here's a quick recap of what is happening!
Phase 1 - Lots to build: 6 single-family homes, 2 condos, 1 townhome building.
- Consists of Stinchcomb Rd, Moose Rd., Thurman Holt Rd., Sandra Ann Way, Gurley Cove.
Phase 2 - Lots to build: 2 single-family homes, 1 commercial lot. We do not know anything more about the commercial lot and what could go there. It has not sold yet.
- Consists of townhome buildings 1-4, Flowers Ave north of ECB, Watkinville Rd, Adeline Rd., Oconee St., Doodle Ln west of Flowers Ave., Gracie Way.
Phase 3 - In-progress with single-family homes and condos. Three townhome buildings have been completed. This phase will include a trail extension near the Lift Station.
- Consists of townhome buildings 5-7, Flowers Ave south of ECB, Betsy Rd., Karly Cv., Vanderscile Rd., Makinaw Rd., Wynn Rd., Doodle Ln. east of Flowers Ave., Lansing Rd., Ricky Ct., Beartooth Way, Childress St., Crumpton Way up to Wynn Rd.
Phase 4 - In-progress with single-family homes, condos and townhomes. While in Phase 7, the detention pond with trail extension will be completed during Phase 4's development.
- Consists of Crumpton Way from Wynn Rd. to Halsey Rd., Bette Rd., Dismukes Rd., Christy St., Robert Ln. from Vanderscile Rd. to Halsey Rd., some condos on ECB.
Phase 5-8 are not in production yet. There will be another detention pond developed in Phase 6. There will also be 1-2 pocket parks developed within these phases. Please note the PUD determines what can go into them.
FM 1660 Entrance has faced delays due to other entities involved in the project. The Developer expects the intersection to be operational by the 2nd Quarter.
Sports Court construction has begun. The estimated completion time is January. Please do not cross the orange fence barriers, as it is not safe.
A map is not available yet, as it changes slightly as the project continues.
|