In the time following our previous update, the wet weather in South East Queensland has continued to be disruptive. While the program was generally maintained throughout April, the rainfall in May was significant.
Our builder, Broad Construction have now structurally completed 100% of the basement slab, columns and external walls to the eastern side of the retail precinct. It is this basement slab that will provide car spaces for patrons accessing the tenancies on the eastern side of the retail precinct. This includes tenancies such as, Dan Murphy’s, Blackwood Espresso, Studio Pilates, and Crafty’s.
The eastern ramp which provides access to the basement slab has also been completed from a structural perspective. The fit off for the car park entrance equipment and line marking will take place towards the end of the project.
Notably, the ground/Level 1 slab pour was completed at the end of May which is a significant achievement.