Golden Eagle Owners,


Having waited more than 120 days so that possible litigation could be filed, in September, after receiving no lawsuits, we began prepping for construction. Water to the park was turned off, mowing was halted, and two applications of a chemical agent to kill the existing turf were made to prepare for the park conversion.


Starting next week, more substantial demo and reconstruction will commence. The tentative construction schedule is as follows:


  • Week of November 4: Demo and removal of all turf. It is expected to take about a month to complete. This will include removing and capping the old irrigation system and removing the controllers from the Golf Club.


  • Week of December 9: DLC's Special Project team will begin installing the new irrigation lines and irrigation heads - approximately 230 irrigation heads and rotors in total. This process will last approximately four to six weeks, lasting until mid or late January 2025.


  • Late January or early February: Sod installation. This is expected to go quickly once the irrigation and earthwork are completed. The intention is to use overseeded sod, which will depend on availability.


As with any project, the above schedule is tentative and subject to change based on weather, digging conditions, and other factors. Changes to the schedule will be communicated on the community website under the projects tab, and periodically through email blasts such as this.

Other Project Details:

  • As with any construction project, there will be noise and dust as DLC works to enhance this space. We encourage you to keep your windows and doors closed when work is underway if you are sensitive to these concerns.


  • On Monday, November 4, a dumpster and portable restroom will be placed in the parking area just west of the park. This is similar to the recent projects, including painting, irrigation, and granite refresh. They will be removed promptly once the project is complete.


  • The Association will gain a significant advantage in maintaining a year-round green space by overhauling the park with an all-new irrigation system. The irrigation will be controlled by one company and geared toward one type of turf rather than having competition between the greens and the surrounding area. With over 200 brand-new irrigation heads and rotors, the coverage will also be significantly enhanced, resulting in better turf and less water waste.


  • Due to drainage concerns, 2" of additional sand will be removed where the putting greens currently sit, and approximately 120 tons of topsoil will be backfilled to ensure water retention to help the new sod thrive.


  • Approximately 51,000 sq ft of new Mid-Iron sod will be installed throughout the entire park, not just in place of the putting greens. This will refresh the entire greenspace and reset the useful life of all major components in the greenspace.

Resources & Communications

Communications and additional resources (such as an FAQ) will be added to future emails, and updated on the project tab of the website as the work progresses.

Community Update | Putting Park
Project Tab | Website
2024 Annual Meeting Presentation
Contact Information
Superstition Mountain is proudly and professionally managed by

Contact Information


Association Office: 480-983-6773



Gate Staff: Superstition.Mountain@CoveySecurity.com 480-983-9270