Crews continue to clear vegetation, excavate and install framework for new retaining walls on Pullman Street between MacArthur Boulevard and McGaw Avenue, and perform earthwork around the MacArthur Boulevard bridge during the day.
In addition, contractors are expected to continue restriping lanes and placing temporary concrete barriers along southbound (SB) SR-55, as well as conduct electrical work in both directions of SR-55. These activities will require lane and ramp closures, nightly, from 10 p.m. to 5 a.m., Monday Nov. 21 and Tuesday, Nov. 22.
In observance of Thanksgiving, there will be no construction activities on Thursday, Nov. 24 and Friday, Nov. 25.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
|