Work is underway to shift traffic on northbound (NB) SR-55 onto newly constructed lanes. The traffic shift requires intermittent nighttime lane and ramp closures, as well as the following connector closures. Drivers should plan for detours and allow extra travel time.

  

9 p.m., Friday, Nov. 13 to 5 a.m., Saturday, Nov. 14:

  • NB I-405 to NB SR-55 HOV connector 
  • SB I-405 to NB SR-55 HOV connector  
  • NB SR-55 to NB I-5 HOV connector 


9 p.m., Saturday, Nov. 14 to 5 a.m., Sunday, Nov. 15:

  • SB I-5 to SB SR-55 connector


This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Westbound MacArthur Boulevard

Southern California Edison is expected to perform electrical work on MacArthur Boulevard, which will require closing westbound MacArthur underneath the freeway from 9 p.m., Saturday, Nov. 14 to 5 a.m., Sunday, Nov. 15.

Permanent Traffic Change to Northbound McFadden Avenue On-Ramp

As part of the NB SR-55 traffic shift, the northbound McFadden Avenue on-ramp will be permanently restriped to eliminate weaving and merging conflicts on NB SR-55.


Once the new striping is in place, motorists using this on-ramp will only be able to access northbound I-5. Access to northbound SR-55 or southbound I-5 will no longer be available from this on-ramp. Motorists traveling to northbound SR-55 or southbound I-5 should use alternate routes. Additional information will be provided in future communications.


To view alternate routes to NB SR-55 and SB I-5, click here.

Southbound SR-55 Traffic Shift

WHAT:

Crews are preparing to demolish and reconstruct the center median of SR-55 between I-405 and I-5 to accommodate a new carpool lane. As part of this work, crews will shift southbound SR-55 traffic onto newly constructed lanes. Intermittent nighttime lane and ramp closures will be required.

 

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.


WHEN:

9 p.m. to 5 a.m. nightly, beginning as early as Saturday, Nov. 14 and continuing for approximately two weeks.

Closures and Detours Map

Bookmark the closures and detours map for quick access to real-time construction information. Click on the construction icons to view activities and closures.

About the Project

OCTA, in cooperation with Caltrans, is improving 4 miles of SR-55 between I-405 and I-5. The project will improve traffic flow and reduce travel time by adding one regular lane and one carpool lane in each direction. Also, the project will add merge lanes between several interchanges and stripe carpool lanes for continuous access, augmenting safety on the freeway by making merging easier. These enhancements are expected to create a better, smoother driving experience for motorists.

 