MacArthur Boulevard Pile Driving Activity

Pile driving is underway along the east side of the MacArthur Boulevard bridge for the foundation of the bridge widening. Work is ongoing, weekdays from 7 a.m. to 5 p.m.


In light of forecasted rain next week, crews plan to drive piles this Saturday, March 18 from 9 a.m. to 4 p.m. To facilitate this work and provide adequate space to maneuver pile driving equipment, crews will close the inside lane of MacArthur in both directions under the freeway, from 10 p.m. Friday, March 17 to 4 p.m. Saturday, March 18.


Learn more about pile driving here.

Construction Activities

Retaining Walls


Crews continue construction on a number of retaining walls along both directions of SR-55. This work includes excavating for footings, building forms, and adding rebar for reinforcement.

Electrical and Drainage Work


Contractors will be continuing nighttime electrical work along both directions of SR-55 for the next several months, as well as daytime construction on drainage systems throughout the area.

Please be advised that this work may be loud. Dates and times are subject to change due to unforeseen operational factors or inclement weather.

Community Presentations

The Public Outreach Team is offering project presentations to businesses, employment centers and community organizations within the project corridor. If your business or group is interested in learning more about project construction and would like a member of the Outreach Team to present, please contact us at 888-371-2555 or SR55Info@octa.net.

Business Spotlight: Casa Bloom Studios

This week's Focus on 55 business spotlight is Casa Bloom Studios, a creative, multi-functional space in the heart of Downtown Santa Ana. Whether you are looking for a workspace, host a workshop, meeting, or special event, Casa Bloom Studios is the place to go!


109 W. 3rd Street, Santa Ana, CA 92701

www.casabloomstudios.com

Info@casabloomstudios.com

Instagram: @casabloomsudios


To learn more about OCTA's Focus on 55 Program, including official rules and eligibility, visit octa.net/Focuson55 or click here to enroll your business today.

About the Project

OCTA, in cooperation with Caltrans, is improving 4 miles of SR-55 between I-405 and I-5. The project will improve traffic flow and reduce travel time by adding one regular lane and one carpool lane in each direction. Also, the project will add merge lanes between several interchanges and stripe carpool lanes for continuous access, augmenting safety on the freeway by making merging easier. These enhancements are expected to create a better, smoother driving experience for motorists.